Area 5 Acres Affordable Group Housing Colony

by Suncity Projects · Sector 102, Gurugram

Not on our price list yet

Possession 30 Jun 2024 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 102, Gurugram0.7 km from Dwarka Expressway, in a straight linePrices and what changed
Registered
24 Aug 2017
Registered by
SUNCITY PROJECTS PVT. LTD.the company that filed it, for Suncity Projects
Timeline
  1. 9 Nov 2015Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 24 Aug 2017Registered with HARERAHARERA, read 4 Nov 2026
  3. 18 Jun 2020Registration valid toHARERA, read 4 Nov 2026
  4. 30 Jun 2024Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside20,234 m² in all, by use
  • Parking5,703 m² · 28%
  • Apartment buildings3,857 m² · 19%
  • Roads3,595 m² · 18%
  • Parks and playgrounds2,879 m² · 14%
  • Pavements1,282 m² · 6%
  • Shops and offices946 m² · 5%
  • Electricity sub-station927 m² · 5%
  • Green belts671 m² · 3%
  • Other usesas the form names them: Community, Creche374 m² · 2%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenPaint / ceramic tiles above counter
  • Lifts2 NOS. in each tower provided
  • FloorsVitrified tiles
  • WallsPaint / ceramic tiles above counter in WASH room
  • BathroomsBrochure attached crome plated fitting, sanitary wares of standard make
  • WindowsComposite (aluminium & steel) with glass
  • Main doorHard wood door frame with flush shutter
  • Electrical fittingsCopper wiring in concealed conduit, modular switches,outlets & junctions boxes

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 102, GurugramSector 102, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.7 km
  • Delhi–Gurugram–SNB RRTS5.8 km
  • Sohna Elevated Corridor (NH-248A)7.0 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Other register states: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is Area 5 Acres Affordable Group Housing Colony registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 91 OF 2017, registered on 24 Aug 2017. Ended 18 Jun 2020. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for Area 5 Acres Affordable Group Housing Colony?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Jun 2024. Its registration runs to 18 Jun 2020; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Area 5 Acres Affordable Group Housing Colony?From the records · Map pin and road lines, read 6 Sep 2026

Area 5 Acres Affordable Group Housing Colony is in Sector 102, Gurugram; the site address declared to HARERA is Sector 102. In a straight line it is about 0.7 km from Dwarka Expressway, 5.8 km from Delhi–Gurugram–SNB RRTS and 7.0 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Area 5 Acres Affordable Group Housing Colony?From the records · HARERA, read 4 Nov 2026

Area 5 Acres Affordable Group Housing Colony is a Suncity Projects project, registered by its company SUNCITY PROJECTS PVT. LTD..

The source ↗Suncity Projects's projects and court record

The records

What the registers hold for Area 5 Acres Affordable Group Housing Colony: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 91 OF 2017: Registration expired. Ended 18 Jun 2020.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 3 OF 2015 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 18 Jun 2020.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 9 Nov 2015.Declared to HARERA, read 29 Oct 2026
The court record of Suncity Projects’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 18 Jun 2020. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 3 OF 2015 validity ended

    Named in this project’s application. Valid to 18 Jun 2020. The register links a completion certificate (LC-IX), dated 27 Dec 2023, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 44 HARERA files, with the dates we read them
Registration no.
91 OF 2017
Registration date
24 Aug 2017
Registration valid till
18 Jun 2020
Declared possession
30 Jun 2024

Declared by the promoter to HARERA

Land area
5 (Acre) (20,234.28 sq m)
FAR
the application prints 224.8, which is not a ratio
licence
3 of 2015
Estimated project cost
₹120.23 crore
Cost of land
₹19.86 crore
Building plans, declared approved
9 Nov 2015
Completion declared for
30 Jun 2024
Declared inventory · 9 types

Declared inventory — 9 types declared, first 8 shown

  • APARTMENT/SHOPS/OTHER BUILDINGS Type A · 96 units · 4,682.26 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type · 103 units · 5,024.32 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type · 103 units · 5,024.32 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type · 95 units · 4,634.13 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type · 71 units · 3,463.57 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type · 95 units · 4,634.13 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type · 95 units · 4,634.13 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type · 51 units · 1,185.708 sq m carpet
Statutory approvals, as declared · 14

Statutory approvals, as declared

  • I. OCCUPATION CERTIFICATE OF WHOLE LICENSE — declared: already been obtained (8 Aug 2019)
  • II. LOI — declared: already been obtained (11 Dec 2013)
  • III. LICENSE — declared: already been obtained (19 Jun 2015)
  • IV. FOREST NOC — declared: already been obtained (11 Aug 2015)
  • V. DC NOC — declared: already been obtained (1 Oct 2015)
  • VI. BUILDING PLAN APPROVAL — declared: already been obtained (9 Nov 2015)
  • VII. ENVIRONMENT CLEARANCE — declared: already been obtained (1 Jul 2016)
  • VIII. CONSENT TO ESTABLISH — declared: already been obtained (1 Aug 2016)
  • IX. FIRE SCHEME APPROVAL — declared: already been obtained (1 Sept 2016)
  • X. SERVICE ESTIMATES — declared: already been obtained (26 Apr 2017)
  • XI. WATER CONNECTION — declared: already been obtained (27 Feb 2019)
  • XII. ELECTRICAL PLAN APPROVAL — declared: already been obtained (15 Apr 2019)
  • XIII. STORM WATER CONNECTION — declared: already been obtained (18 Oct 2019)
  • XIV. SEWER CONNECTION — declared: already been obtained (19 Nov 2019)
On file with HARERA · 44 files

On file with HARERA (44)

Plans

Site plan

1 file
Approved Site Plan26 Nov 2019

Layout plan

2 files
Layout4 Feb 2020Latest Layout Plan26 Nov 2019

Zoning plan

1 file
Zoning Plan26 Nov 2019

Demarcation plan

1 file
Demarcation Plan26 Nov 2019

Building plans

5 files
Elevation Section Block E,g,h4 Feb 2020Elevation Section Block B C D4 Feb 2020Elevation, Sections Creche & Community4 Feb 2020

Floor plans

5 files
Ground Floor Block A4 Feb 2020Typical, Tarrece & Area Block B to E & G, H4 Feb 2020Ground Floor Block F4 Feb 2020

Services

Sewerage and drainage

2 files
Drainage & Water Supply4 Feb 2020Sewer4 Feb 2020

Landscape and green areas

1 file
Layout Plan & Green Area4 Feb 2020

Service plans

3 files
Service Estimate Approval Letter4 Feb 2020Service Estimate4 Feb 2020Service Plans on the Layout26 Nov 2019

Approvals and clearances

Occupation certificate (OC)

3 files
OC uploaded6 Sept 2023Letter to RERA for Occupation Certificate Submission7 Dec 2019Occupation Certificate26 Nov 2019

Completion certificate (CC)

1 file
Completion Certificate5 Aug 2024

DTCP licence

3 files
LOI 5.00 Acres4 Feb 2020LC-IV & Iva4 Feb 2020Licence Copy with Land Schedule26 Nov 2019

Environment clearance

1 file
Environmental Clearance4 Feb 2020

Fire safety

1 file
Fire Fighting Scheme Approval4 Feb 2020

Other NOCs and clearances

3 files
AAI NOC4 Feb 2020Forest NOC4 Feb 2020Consent to Establish26 Nov 2019

Land records

Land records

2 files
No- Encumbrance Certificate4 Feb 2020Revenue Record Entry of Licence and Collaboration26 Nov 2019

Money

Accounts and finance

6 files
Demand Draft Deficit Amount4 Feb 2020CA Certificate on the Application’s Figures4 Feb 2020Board Resolution for Bank4 Feb 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit26 Nov 2019

Other filings

Other filings

2 files
BR - Iiii4 Feb 2020Commercial Block4 Feb 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

3 OF 2015 · Suncity Projects Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 18 Jun 2020

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 7 Dec 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

3 OF 2015: 7 parcels, 5 acres in all, in Dhankot (hadbast 49), tehsil Kadipur.

The licence register prints the same licensed area, 5 acres.

  • 57//228 kanal
  • 79//113 kanal 4 marla
  • 79//125 kanal 16 marla
  • 79//28 kanal
Show the other 3 parcels
  • 79//34 kanal 11 marla
  • 79//82 kanal 8 marla
  • 79//98 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Dhankot (hadbast 49), tehsil Kadipur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 57//22.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, residential flat
₹6,000 per sq ft

Sector 102, collector rates effective 1 Apr 2026, Kadipur tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan26 Nov 2019

Layout plan

2 files
Layout4 Feb 2020Latest Layout Plan26 Nov 2019

Building plans

5 files
Elevation Section Block E,g,h4 Feb 2020Elevation Section Block B C D4 Feb 2020Elevation, Sections Creche & Community4 Feb 2020Elevation Section Block A4 Feb 2020Approved Building Plans, Full Set26 Nov 2019

Floor plans

5 files
Ground Floor Block A4 Feb 2020Typical, Tarrece & Area Block B to E & G, H4 Feb 2020Ground Floor Block F4 Feb 2020Ground Floor Block B to E & G, H4 Feb 2020Typical, Tarrece & Area Block F4 Feb 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (44 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/996 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Suncity Projects

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.