Sobha City-Phase V

by Sobha · Sector 108, Gurugram

Not on our price list yet

Possession 31 Dec 2026 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 108, Gurugram2.7 km from Dwarka Expressway, in a straight linePrices and what changed
Carpet area
1,309–1,512 sq ft
In m²about 122–140 m², as declared
Registered
21 Sep 2020
Registered by
SOBHA LIMITEDthe company that filed it, for Sobha
Timeline
  1. 19 Jan 2016Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 21 Sep 2020Registered with HARERAHARERA, read 4 Nov 2026
  3. 31 Dec 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

192homes, 1,309 to 1,512 sq ft of carpet area
  • 1,000–1,500 sq ft1,309 sq ft96
  • 1,500–2,000 sq ft1,512 sq ft96

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.102 acres in all, by use
  • Parks and playgrounds1.363 acres · 27%
  • Other uses1.018 acres · 20%
  • Pavements0.849 acres · 17%
  • Roads0.635 acres · 12%
  • Green belts0.602 acres · 12%
  • Apartment buildings0.33 acres · 6%
  • Sewage and waste treatment0.183 acres · 4%
  • Parking0.121 acres · 2%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningPower connection MADE available for split AC in living, dining and all the bed rooms.
  • KitchenCeramic tile flooring, wall tiling & plastic emulsion paint for ceiling.
  • LiftsCapacity - 1 no. of 15 passenger & 2 NOS. of 8 passenger lift of reputed make.
  • FloorsNatural / engineered stone flooring and skirting/ laminated wooden flooring and skirting / vitrified tile flooring and skirting /ceramic tile.
  • WallsFor internal walls, plastic emulsion paint / ceramic wall tiling wherever applicable & textured paint for external walls.
  • BathroomsReputed make of CP fittings & sanitary WARE.
  • WindowsHeavy-DUTY aluminium glazed sliding windows & french windows MADE from specially designed and manufactured sections.
  • Main doorFrame – timber. shutters – with both side masonite SKIN.

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 108, GurugramSector 108, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20252.7 km
  • Delhi–Gurugram–SNB RRTS7.5 km
  • Sohna Elevated Corridor (NH-248A)9.1 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 11 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 4
  • Registered, no OC or CC yet: 6
  • Other register states: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is Sobha City-Phase V registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/410/142/2020/26, registered on 21 Sep 2020. Valid to 31 Dec 2026.

The source ↗
What is the possession timeline for Sobha City-Phase V?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2026. Its registration runs to 31 Dec 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Sobha City-Phase V?From the records · Map pin and road lines, read 6 Sep 2026

Sobha City-Phase V is in Sector 108, Gurugram; the site address declared to HARERA is Revenue Estate Of Babupur Village, Village Babupur, Sector-108, Gurugram, Haryana. In a straight line it is about 2.7 km from Dwarka Expressway, 7.5 km from Delhi–Gurugram–SNB RRTS and 9.1 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Sobha City-Phase V?From the records · HARERA, read 4 Nov 2026

Sobha City-Phase V is a Sobha project, registered by its company SOBHA LIMITED.

The source ↗Sobha's projects and court record

The records

What the registers hold for Sobha City-Phase V: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/410/142/2020/26: Registered. Valid to 31 Dec 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 107 OF 2008 is on the DTCP register, valid to 26 May 2028.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 19 Jan 2016, building plans 19 Jan 2016.Declared to HARERA, read 29 Oct 2026
The court record of Sobha’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 31 Dec 2026. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 22 HARERA files, with the dates we read them
Registration no.
GGM/410/142/2020/26
Registration date
21 Sept 2020
Registration valid till
31 Dec 2026
Declared possession
31 Dec 2026

Declared by the promoter to HARERA

Land area
5.10183 (Acre) (20,646.37 sq m)
FAR
0.21 proposed of 1.75 permissible
licence
107 of 2008 (26.05.2020)
Estimated project cost
₹357.94 crore
Cost of land
₹134.51 crore
Layout plan, declared approved (field 5a)
19 Jan 2016
Building plans, declared approved
19 Jan 2016
Construction to start
15 Jun 2020
Completion declared for
31 Dec 2026
Declared inventory · 2 types

Declared inventory

  • Apartment/Shops/Other Buildings · 96 units · 121.58 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 96 units · 140.47 sq m carpet · 2 towers · one flat
Statutory approvals, as declared · 11

Statutory approvals, as declared

  • I. LICENCE — declared: already been obtained (27 May 2008)
  • II. FOREST NOC — declared: already been obtained (23 Oct 2013)
  • III. NATURAL CONSERVATION ZONE — declared: already been obtained (5 Nov 2013)
  • IV. ELECTRICAL LOAD AVAILABILITY — declared: already been obtained (6 Oct 2016)
  • V. HUDA CONSTRUCTION WATER NOC — declared: already been obtained (30 Apr 2017)
  • VI. FIRE SCHEME APPROVAL — declared: already been obtained (24 May 2017)
  • VII. ENVIRONMENT CLEARANCE — declared: already been obtained (29 Aug 2017)
  • VIII. AIRPORT HEIGHT CLEARANCE — declared: already been obtained (24 Nov 2017)
  • IX. CONSENT TO ESTABLISH — declared: already been obtained (30 Nov 2017)
  • X. SERVICE ESTIMATES PLAN — declared: already been obtained (12 Mar 2019)
  • XI. ELECTRICAL CONNECTION APPROVAL — declared: already been obtained (15 Nov 2019)
On file with HARERA · 22 files

On file with HARERA (22)

Plans

Site plan

1 file
Approved Site Plan17 Jun 2020

Layout plan

1 file
Latest Layout Plan17 Jun 2020

Zoning plan

1 file
Zoning Plan17 Jun 2020

Demarcation plan

1 file
Demarcation Plan17 Jun 2020

Building plans

2 files
Building Plan Approval17 Jun 2020Approved Building Plans, Full Set17 Jun 2020

Services

Service plans

2 files
Service Plans on the Layout17 Jun 2020Service Estimates Plan17 Jun 2020

Approvals and clearances

DTCP licence

3 files
LC-IV17 Jun 2020Licence Copy with Land Schedule17 Jun 2020LOI17 Jun 2020

Environment clearance

1 file
Environment Clearance17 Jun 2020

Fire safety

1 file
Fire NOC17 Jun 2020

Other NOCs and clearances

2 files
Forest NOC17 Jun 2020Airport Height Clearance17 Jun 2020

Land records

Land records

2 files
Revenue Record Entry of Licence and Collaboration17 Jun 2020Assignment of Development Right17 Jun 2020

Money

Accounts and finance

3 files
CA Certificate on the Application’s Figures17 Jun 2020Cash Flow Statement17 Jun 2020Non-Default Certificate from a CA17 Jun 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit17 Jun 2020

Company papers

1 file
Board Resolution17 Jun 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

107 OF 2008 · Shobha Ltd. (Transferred from Chintel India Ltd. on 19/04/2017) · GURGAON-MANESAR

Licence valid to 26 May 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 17 Jun 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

107 OF 2008

DTCP’s page showed no land schedule for licence 107 OF 2008 when Bhumiq read it on 18 Oct 2026. verify at source

Collector rate, residential flat
₹7,700 per sq ft

Sector 108, collector rates effective 1 Apr 2026, Gurugram tehsil. 2 tehsil lists price this sector; this is the higher. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan17 Jun 2020

Layout plan

1 file
Latest Layout Plan17 Jun 2020

Building plans

2 files
Building Plan Approval17 Jun 2020Approved Building Plans, Full Set17 Jun 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (22 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1380 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Sobha

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.