TRL RESIDENTIAL PLOTTED COLONY
by Trl Riceland · Sector 76, Gurugram
Not on our price list yet
Possession 21 Oct 2022 · as the developer declared it to HARERA
About this project
Key facts
- Location
- Sector 76, Gurugram0.9 km from Delhi–Gurugram–SNB RRTS, in a straight line
- Registered by
- TRL RICELAND PRIVATE LIMITEDthe company that filed it, for Trl Riceland
- 21 Oct 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026
- 12 Feb 2028Registration valid toHARERA, read 4 Nov 2026
Amenities and specifications
How the land is set aside and what comes in each home, as the developer declared them to HARERA.
- Plots for sale13.27 acres · 44%
- Other usesas the form names them: EWS land, Service building with STP, Others, Community land, Twenty four meter road7.34 acres · 25%
- Parks and playgrounds4.76 acres · 16%
- Roads3.84 acres · 13%
- Shops and offices0.6 acres · 2%
- Electricity sub-station0.1 acres · under 1%
The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
- Delhi–Gurugram–SNB RRTS0.9 km
- Dwarka ExpresswayOpen, 17 Aug 20251.6 km
- Sohna Elevated Corridor (NH-248A)5.5 km
Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.
Map data © OpenStreetMap contributors.
The builder
- OC or CC dispatched: 1
Other projects nearby
8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.
| Project | Builder | Distance | Stage | Asking rate | Possession |
|---|---|---|---|---|---|
| Whiteland Corporation | Same sector | — | — | 30 Jun 2031 | |
Suncity Avenue 76No photo on file yet | Suncity Projects | Same sector | — | — | 30 Sep 2024 |
| Whiteland Corporation | Same sector | — | ₹14,000/sq ft | 30 Jun 2027 | |
No photo of the project on file yet | Pyramid Infratech | Same sector | — | — | 24 Feb 2024 |
| Whiteland Corporation | Same sector | — | — | 31 Dec 2026 | |
| Whiteland Corporation | Same sector | — | — | 31 Dec 2026 | |
| Whiteland Corporation | Same sector | Under construction | ₹15,500/sq ft | 31 Dec 2030 | |
SEASONSNo photo on file yet | Keystone World | 1.1 kmto its sector’s point | — | — | 30 Sep 2029 |
Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.
Questions buyers ask
Is TRL RESIDENTIAL PLOTTED COLONY registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as GGM/696/428/2023/40. Valid to 12 Feb 2028.
The source ↗What is the possession timeline for TRL RESIDENTIAL PLOTTED COLONY?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 21 Oct 2022. Its registration runs to 12 Feb 2028; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around TRL RESIDENTIAL PLOTTED COLONY?From the records · Map pin and road lines, read 6 Sep 2026
TRL RESIDENTIAL PLOTTED COLONY is in Sector 76, Gurugram; the site address declared to HARERA is 42nd Km Stone, Nh-48, Sector-76. In a straight line it is about 0.9 km from Delhi–Gurugram–SNB RRTS, 1.6 km from Dwarka Expressway and 5.5 km from Sohna Elevated Corridor (NH-248A).
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building TRL RESIDENTIAL PLOTTED COLONY?From the records · HARERA, read 4 Nov 2026
TRL RESIDENTIAL PLOTTED COLONY is a Trl Riceland project, registered by its company TRL RICELAND PRIVATE LIMITED.
The source ↗Trl Riceland's projects and court recordThe records
What the registers hold for TRL RESIDENTIAL PLOTTED COLONY: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration GGM/696/428/2023/40: Registered. Valid to 12 Feb 2028.HARERA, read 4 Nov 2026 · See it on HARERA ↗
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 16 HARERA files, with the dates we read them
- Registration no.
- GGM/696/428/2023/40
- Registration valid till
- 12 Feb 2028
- Declared possession
- 21 Oct 2022
Declared by the promoter to HARERA
- Land area
- 29.91 (Acre) (1,21,041.48 sq m)
- FAR
- 1 proposed of 1 permissible
- licence
- 87 of 20117 dated 23.10.2017
- Estimated project cost
- ₹147.81 crore
- Cost of land
- ₹1.66 crore
- Construction to start
- 29 Jan 2020
- Completion declared for
- 21 Oct 2022
Statutory approvals, as declared · 14
Statutory approvals, as declared
- I. LC V — declared: already been obtained (23 Oct 2017)
- II. ZONING PLAN FOR PLOTTED COLONY — declared: already been obtained (9 Oct 2018)
- III. ZONING PLAN FOR SERVICE BUILDING — declared: already been obtained (2 Dec 2020)
- IV. ELECTRIFICATION PLAN — declared: already been obtained (29 Jan 2020)
- V. SERVICE PLAN ESTIMATE — declared: already been obtained (8 Aug 2019)
- VI. NON APPLICABILITY OF SEIAA — declared: already been obtained (7 Dec 2016)
- VII. GIFT DEED FOR COMMUNITY AND EWS — declared: already been obtained (10 Dec 2020)
- VIII. GIFT DEED FOR SWITCHING STATION — declared: already been obtained (13 Oct 2021)
- IX. NOC FIRE FOR SERVICE BUILDING — declared: already been obtained (22 Jul 2022)
- X. NOC FROM FOREST DEPT. — declared: already been obtained (6 Oct 2017)
- XI. GIFT DEED FOR 24 METER INTERNAL SECTOR ROAD — declared: already been obtained (27 Sept 2022)
- XII. OCCUPATION CERTIFICATE FOR SERVICE BUILDING — declared: already been obtained (11 Oct 2022)
- XIII. COMPLETION CERTIFICATE FOR PLOTTED COLONY — declared: already been obtained (21 Oct 2022)
- XIV. CEI APPROVAL — declared: already been obtained (19 Jul 2022)
On file with HARERA · 16 files
On file with HARERA (16)
Plans
Site plan
1 fileLayout plan
1 fileZoning plan
1 fileDemarcation plan
1 fileServices
Sewerage and drainage
2 filesWater supply
1 fileElectricity
1 fileRoads
1 fileService plans
2 filesApprovals and clearances
Completion certificate (CC)
1 fileDTCP licence
1 fileMoney
Accounts and finance
1 fileThe promoter’s papers
Declarations and affidavits
1 fileOther filings
Other filings
1 fileThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
The promoter declared 87 of 20117 dated 23.10.2017. We could not read a licence number from that, so nothing is claimed about it here.
declared in the registration application (Form REP-I), Gurugram bench · submitted 1 Dec 2022 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026
Collector rate
No one collector rate can be matched to this project's type.
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
1 fileLayout plan
1 fileAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (16 in all), none is a building plan, a floor plan or a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/2003 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Trl Riceland
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.