About this project

Key facts

Location
Sector 73, Gurugram-Manesar1.9 km from Delhi–Gurugram–SNB RRTS, in a straight linePrices and what changed
Registered by
DLF HOME DEVELOPERS LIMITEDthe company that filed it, for DLF Home Developers
Timeline
  1. 13 Sep 2022Layout and building plans approveddeclared to HARERA, read 5 Nov 2026
  2. 8 Sep 2027Possession, as declareddeclared to HARERA, read 5 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside2.98 acres in all, by use
  • Plots for sale1.04 acres · 35%
  • Roads1.01 acres · 34%
  • Parks and playgrounds0.45 acres · 15%
  • Other usesas the form names them: Open0.4 acres · 13%
  • Electricity sub-station0.04 acres · 1%
  • Sewage and waste treatment0.04 acres · 1%

The land-use table of the HARERA application, declared to HARERA, read 5 Nov 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 73, Gurugram-ManesarThe licensed land, as mapped by DTCP (read 5 Nov 2026) · tcpharyana.gov.inOpen in Google Maps
Roads and rail lines
  • Delhi–Gurugram–SNB RRTS1.9 km
  • Dwarka ExpresswayOpen, 17 Aug 20252.1 km
  • Sohna Elevated Corridor (NH-248A)3.0 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 11 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 7
  • Registered, no OC or CC yet: 4

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is ALAMEDA CENTRAL registered with HARERA?From the records · HARERA, read 5 Nov 2026

HARERA lists it as GGM/632/364/2022/107. Valid to 8 Sep 2027.

The source ↗
What is the possession timeline for ALAMEDA CENTRAL?From the records · HARERA, read 5 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 8 Sep 2027. Its registration runs to 8 Sep 2027; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ALAMEDA CENTRAL?From the records · Map pin and road lines, read 6 Sep 2026

ALAMEDA CENTRAL is in Sector 73, Gurugram-Manesar; the site address declared to HARERA is Sector 73, Gurugram. In a straight line it is about 1.9 km from Delhi–Gurugram–SNB RRTS, 2.1 km from Dwarka Expressway and 3.0 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ALAMEDA CENTRAL?From the records · HARERA, read 5 Nov 2026

ALAMEDA CENTRAL is a DLF Home Developers project, registered by its company DLF HOME DEVELOPERS LIMITED.

The source ↗DLF Home Developers's projects and court record

The records

What the registers hold for ALAMEDA CENTRAL: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/632/364/2022/107: Registered. Valid to 8 Sep 2027.HARERA, read 5 Nov 2026 · See it on HARERA ↗
  • Land licence 139 OF 2022 is on the DTCP register, valid to 8 Sep 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 13 Sep 2022, building plans 13 Sep 2022.Declared to HARERA, read 5 Nov 2026
The court record of DLF Home Developers’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 72 HARERA files, with the dates we read them
Registration no.
GGM/632/364/2022/107
Registration valid till
8 Sept 2027
Declared possession
8 Sept 2027

Declared by the promoter to HARERA

Land area
2.98125 (Acre) (12,064.69 sq m)
FAR
1.5 proposed of 1.5 permissible
licence
139 of 2022
Estimated project cost
₹71.25 crore
Cost of land
₹27.02 crore
Layout plan, declared approved (field 5a)
13 Sept 2022
Building plans, declared approved
13 Sept 2022
Construction to start
1 Apr 2023
Completion declared for
8 Sept 2027
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (9 Sept 2022)
  • II. LAYOUT — declared: already been obtained (13 Sept 2022)
On file with HARERA · 72 files

On file with HARERA (72)

Plans

Site plan

2 files
Site Plan & Calculations22 Jan 2025Approved Site Plan14 Sept 2022

Layout plan

2 files
Approved Layout Plan22 Jan 2025Latest Layout Plan14 Sept 2022

Demarcation plan

2 files
Demarcation22 Jan 2025Demarcation Plan14 Sept 2022

Building plans

2 files
Standard Design22 Jan 2025Approval of Standard Design22 Jan 2025

Services

Sewerage and drainage

8 files
SPE 2.98-Sewage Layout Plan22 Jan 2025SPE 2.98-StormWater Layout Plan22 Jan 2025SPE 0.175- Sewerage22 Jan 2025

Water supply

5 files
SPE 2.98-Flushing & Irrigation Supply Layout22 Jan 2025SPE 0.175- Domestic Water Supply22 Jan 2025SPE 0.175- Recyled Water22 Jan 2025

Electricity

1 file
Electrical Load22 Nov 2022

Roads

3 files
SPE 2.98-Road Layout22 Jan 2025SPE 0.175- Road22 Jan 2025Road Layout22 Nov 2022

Service plans

6 files
SPE of 2.98125 acres-Almeda Central22 Jan 2025SPE of 2.98125 acres-Alameda Central22 Jan 2025SPE 0.175- Approval Letter & Estimates22 Jan 2025

Approvals and clearances

Completion certificate (CC)

1 file
Completion Certificate20 Mar 2026

DTCP licence

7 files
Addendum to Registration Certificate after Grant of Additional License24 Jan 2025LC- IV Bilateral Agreement for Lic 237 of 202322 Jan 2025Licence no 237 of 202322 Jan 2025

Fire safety

2 files
SPE 2.98-Domestic & Firefighting Layout22 Jan 2025Domestic Fire Fitting22 Nov 2022

Land records

Land records

11 files
Aks Shizra22 Jan 2025Jamabandi Begumpur Khatola 2018-19 (002)22 Jan 2025Jamabandi Begumpur Khatola 2018-1922 Jan 2025

Sales papers

Payment plan

1 file
Payment Plan1 Oct 2022

Money

Accounts and finance

8 files
Cash Flow22 Jan 2025Estimated Cost of project22 Jan 2025No Dues Certificate Alameda Central22 Jan 2025

Timeline and progress

Construction schedule

2 files
Pert Chart22 Jan 2025PERT7 Dec 2022

The promoter’s papers

Declarations and affidavits

4 files
Bank Undertaking22 Jan 2025The Promoter’s Declaration on Affidavit9 Dec 2022Rep II7 Dec 2022Promoter Affidavit7 Dec 2022

Other filings

Other filings

5 files
1639-2024 (A-H)24 Jan 2025SCO Public Toilet Block22 Jan 2025SCO Type A22 Jan 2025

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

139 OF 2022 · DLF Home Developers Ltd. · GURGAON-MANESAR

Licence valid to 8 Sept 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 15 Sept 2022 · read 5 Nov 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 5 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

139 OF 2022: 6 parcels, 2.9813 acres in all, in Bagampur khatola (hadbast 101), tehsil Kadipur.

The licence register prints the same licensed area, 2.9813 acres.

  • 39//19/33 marla
  • 39//208 kanal
  • 40//16/11 kanal
  • 40//16/2/15 kanal 12 marla
Show the other 2 parcels
  • 40//24/2/21 kanal 2 marla
  • 40//258 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Bagampur khatola (hadbast 101), tehsil Kadipur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 39//19/3.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type. See the collector rates for Sector 73.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Site Plan & Calculations22 Jan 2025Approved Site Plan14 Sept 2022

Layout plan

2 files
Approved Layout Plan22 Jan 2025Latest Layout Plan14 Sept 2022

Building plans

2 files
Standard Design22 Jan 2025Approval of Standard Design22 Jan 2025

Payment plan

1 file
Payment Plan1 Oct 2022

Among the uploads Bhumiq read from HARERA's page on 5 Nov 2026 (72 in all), none is a floor plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2089 · read 5 Nov 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on DLF Home Developers

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.