Possession 31 Dec 2018 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 109, Gurugram0.8 km from Dwarka Expressway, in a straight linePrices and what changed
Carpet area
about 1,664 sq ft
In m²about 154.6 m², the average flat, as declared
Registered
24 Jan 2019
Registered by
CHINTELS INDIA LTDthe company that filed it, for Chintels India
Timeline
  1. 14 Feb 2017Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2018Possession, as declareddeclared to HARERA, read 29 Oct 2026
  3. 24 Jan 2019Registered with HARERAHARERA, read 4 Nov 2026
  4. 31 Dec 2023Registration valid toHARERA, read 4 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

In each home
  • Air-conditioningCopper piping fitting only. no AC
  • Kitchen2FT tiles above counter, granite counter, sink, chimney/hob
  • Kitchen appliancesChimney/hob
  • LiftsBranded lift thyssen & krupp
  • FloorsEngineered marble
  • WallsPaint
  • BathroomsTiles, POP paint, granite counter, branded CP fittings
  • WindowsGlass

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 109, GurugramSector 109, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.8 km
  • Delhi–Gurugram–SNB RRTS5.3 km
  • Sohna Elevated Corridor (NH-248A)7.8 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 3 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 3

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is Chintels Serenity Pocket B Phase II registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/307/39/2019/01, registered on 24 Jan 2019. Ended 31 Dec 2023. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for Chintels Serenity Pocket B Phase II?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2018. Its registration runs to 31 Dec 2023; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Chintels Serenity Pocket B Phase II?From the records · Map pin and road lines, read 6 Sep 2026

Chintels Serenity Pocket B Phase II is in Sector 109, Gurugram; the site address declared to HARERA is Sector - 109, Gurugram. In a straight line it is about 0.8 km from Dwarka Expressway, 5.3 km from Delhi–Gurugram–SNB RRTS and 7.8 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Chintels Serenity Pocket B Phase II?From the records · HARERA, read 4 Nov 2026

Chintels Serenity Pocket B Phase II is a Chintels India project, registered by its company CHINTELS INDIA LTD.

The source ↗Chintels India's projects and court record

The records

What the registers hold for Chintels Serenity Pocket B Phase II: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/307/39/2019/01: Registration expired. Ended 31 Dec 2023.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 50 OF 2012 is on the DTCP register: Licence lapsed; the register prints its validity to 16 May 2025.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 14 Feb 2017.Declared to HARERA, read 29 Oct 2026
The court record of Chintels India’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 31 Dec 2023. HARERA Gurugram, read 4 Nov 2026. Source

  • Red flag: Licence 50 OF 2012 lapsed

    Named in this project’s application. Valid to 16 May 2025; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 13 HARERA files, with the dates we read them
Registration no.
GGM/307/39/2019/01
Registration date
24 Jan 2019
Registration valid till
31 Dec 2023
Declared possession
31 Dec 2018

Declared by the promoter to HARERA

Land area
6.5 (Acre) (26,304.57 sq m)
FAR
the application prints 11.5, which is not a ratio
licence
250 of 2007 (2.11.2007) 50 of 2012 (17.05.2012)
Estimated project cost
₹233.00 crore
Cost of land
₹13.00 crore
Building plans, declared approved
14 Feb 2017
Completion declared for
31 Dec 2018
Declared inventory · 1 type

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENTS · 444 units · 68,643.02 sq m carpet · total for 444 flats, about 154.6 m² each
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. ALL APPROVAL DONE — declared: already been obtained (14 Feb 2017)
On file with HARERA · 13 files

On file with HARERA (13)

Plans

Site plan

1 file
Approved Site Plan30 Nov 2018

Layout plan

1 file
Latest Layout Plan30 Nov 2018

Zoning plan

1 file
Zoning Plan30 Nov 2018

Demarcation plan

1 file
Demarcation Plan30 Nov 2018

Building plans

1 file
Approved Building Plans, Full Set30 Nov 2018

Services

Service plans

1 file
Service Plans on the Layout30 Nov 2018

Approvals and clearances

Occupation certificate (OC)

1 file
Occupation Certificate5 Dec 2024

DTCP licence

1 file
Licence Copy with Land Schedule8 Feb 2019

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration30 Nov 2018

Money

Accounts and finance

3 files
Cash Flow Statement30 Nov 2018Non-Default Certificate from a CA30 Nov 2018CA Certificate on the Application’s Figures30 Nov 2018

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit8 Feb 2019

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

250 OF 2007 · Chintels India · GURGAON-MANESAR

Licence valid to 1 Nov 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

50 OF 2012 · Chintels India · GURGAON-MANESAR

Licence valid to 16 May 2025

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 30 Nov 2018 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the 2 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

250 OF 2007

DTCP’s page showed no land schedule for licence 250 OF 2007 when Bhumiq read it on 18 Oct 2026. verify at source

50 OF 2012: 15 parcels, 8.2937 acres in all, in Babupur (hadbast 60), tehsil Gurgaon.

The licence register prints the same licensed area, 8.29 acres.

  • 2//2111 marla
  • 3//248 kanal 4 marla
  • 3//253 kanal 18 marla
  • 11//148 kanal
Show the other 11 parcels
  • 11//17/21 kanal 4 marla
  • 11//4/16 kanal 18 marla
  • 11//4/21 kanal 2 marla
  • 11//5/16 kanal 18 marla
  • 11//5/21 kanal 2 marla
  • 11//6/16 kanal 16 marla
  • 11//78 kanal
  • 11//8/12 kanal 16 marla
  • 12//1/16 kanal 14 marla
  • 12//1/21 kanal 2 marla
  • 12//10/13 kanal 2 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Babupur (hadbast 60), tehsil Gurgaon. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 2//21.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, residential flat
₹7,700 per sq ft

Sector 109, collector rates effective 1 Apr 2026, Gurugram tehsil. 2 tehsil lists price this sector; this is the higher. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan30 Nov 2018

Layout plan

1 file
Latest Layout Plan30 Nov 2018

Building plans

1 file
Approved Building Plans, Full Set30 Nov 2018

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (13 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/314 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Chintels India

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.