Skip to content

Not on our price list yet

Possession 31 Dec 2033 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 88A, Gurugram0.7 km from Dwarka Expressway, in a straight line
Carpet area
302–4,086 sq ft
In m²about 28–380 m², as declared
Timeline
  1. 12 Sep 2025Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Sep 2033Registration valid toHARERA, read 4 Nov 2026
  3. 31 Dec 2033Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

268homes, 302 to 4,086 sq ft of carpet area
  • Under 1,000 sq ft302–367 sq ft11
  • 1,000–1,500 sq ft1,414 sq ft4
  • 1,500–2,000 sq ft1,518 sq ft158
  • 2,000–2,500 sq ft2,020–2,098 sq ft81
  • 3,000 sq ft and above4,044–4,086 sq ft14

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 5 rows of a single unit and 66 units under 25 m², because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside2.978 acres in all, by use
  • Apartment buildings1.116 acres · 37%
  • Pavements0.677 acres · 23%
  • Parks and playgrounds0.602 acres · 20%
  • Roads0.58 acres · 19%
  • Other usesas the form names them: Security0.003 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningSplit AC
  • KitchenVitrified tiles, vitrified tiles 2' above kitchen counter, REST of walls in acrylic emulsion paint¸ acrylic emulsion paint¸ prefabricated modular door with frame or flush door with laminate / paint and hardwood frame, aluminium / UPVC glazing with performance glass
  • Lifts4 flats per floor, 4 lifts per floor
  • FloorsVitrified tile, laminate wooden flooring, anti skid vitrified tiles, ceramic tile
  • WallsPremium acrylic emulsion/ distemper/ cladding
  • BathroomsVitrified tile upto false ceiling, moisture resistant false ceiling with acrylic emulsion paint, sink & washbasin
  • WindowsFull height windows- aluminium powder coated sections
  • Main doorMAIN door to FLAT - hardwood frame with veneered flush door/ as per drawing

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 88A, GurugramSector 88A, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.7 km
  • Delhi–Gurugram–SNB RRTS4.5 km
  • Sohna Elevated Corridor (NH-248A)7.9 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 2

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is DEVASYA BHARAT registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/1017/749/2025/120. Valid to 30 Sep 2033.

The source ↗
What is the possession timeline for DEVASYA BHARAT?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2033. Its registration runs to 30 Sep 2033; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around DEVASYA BHARAT?From the records · Map pin and road lines, read 6 Sep 2026

DEVASYA BHARAT is in Sector 88A, Gurugram; the site address declared to HARERA is Sector 88a, Gurugram. In a straight line it is about 0.7 km from Dwarka Expressway, 4.5 km from Delhi–Gurugram–SNB RRTS and 7.9 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building DEVASYA BHARAT?From the records · HARERA, read 4 Nov 2026

DEVASYA BHARAT is a Devasya Developers Pvt. Ltd (Formerly Known As Next Generation Projects Pvt Ltd) project.

The source ↗Devasya Developers Pvt. Ltd (Formerly Known As Next Generation Projects Pvt Ltd)'s projects and court record

The records

What the registers hold for DEVASYA BHARAT: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/1017/749/2025/120: Registered. Valid to 30 Sep 2033.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 141 OF 2024 is on the DTCP register, valid to 10 Nov 2029.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 12 Sep 2025.Declared to HARERA, read 29 Oct 2026
The court record of Devasya Developers Pvt. Ltd (Formerly Known As Next Generation Projects Pvt Ltd)’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 65 HARERA files, with the dates we read them
Registration no.
GGM/1017/749/2025/120
Registration valid till
30 Sept 2033
Declared possession
31 Dec 2033

Declared by the promoter to HARERA

Land area
2.977 (Acre) (12,047.49 sq m)
FAR
3.61 proposed of 3.62 permissible
licence
141 of 2024 DATED 11.11.2024
Estimated project cost
₹1226.73 crore
Cost of land
₹312.81 crore
Building plans, declared approved
12 Sept 2025
Construction to start
1 Dec 2025
Completion declared for
31 Dec 2033
Declared inventory · 20 types

Declared inventory — 20 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 4 units · 131.4 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 158 units · 141.05 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 1 unit · 177.34 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 14 units · 187.66 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 13 units · 189.56 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 54 units · 194.88 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 7 units · 375.7 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 7 units · 379.62 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 14

Statutory approvals, as declared

  • I. HUDA CONSTRUCTION WATER NOC — declared: already been obtained (30 Jun 2025)
  • II. WATER SUPPLY — declared: already been obtained (28 Nov 2024)
  • III. SEWAGE DISPOSAL — declared: already been obtained (26 Nov 2024)
  • IV. STORM WATER DRAINAGE — declared: already been obtained (26 Nov 2024)
  • V. ELECTRICAL LOAD — declared: already been obtained (28 Nov 2024)
  • VI. ENVIRONMENT CLEARANCE — declared: already been obtained (20 Feb 2025)
  • VII. AIRPORT HEIGHT CLEARANCE — declared: already been obtained (21 Oct 2024)
  • VIII. FOREST NOC — declared: already been obtained (9 Oct 2024)
  • IX. LOI — declared: already been obtained (5 Aug 2024)
  • X. BR-III — declared: already been obtained (12 Sept 2025)
  • XI. LICENSE — declared: already been obtained (11 Nov 2024)
  • XII. FIRE SCHEME APPROVAL — declared: already been obtained (16 Oct 2025)
  • XIII. LETTER OF PHASING PLAN — declared: already been obtained (13 Jan 2025)
  • XIV. SERVICE PLAN AND ESTIMATES — declared: applied for but yet to receive (19 Sept 2025)
On file with HARERA · 65 files

On file with HARERA (65)

Plans

Site plan

8 files
Site Plan Road Layout7 Oct 2025Site Plan Storm Layout7 Oct 2025Site Plan Domestic Water Supply Layout7 Oct 2025

Layout plan

3 files
Approved Phasing Plan26 Sept 2025Letter of Phasing Plan26 Sept 2025Latest Layout Plan24 Sept 2025

Zoning plan

1 file
Zoning Plan22 Sept 2025

Demarcation plan

1 file
Demarcation Plan22 Sept 2025

Building plans

6 files
Section Aa26 Sept 2025Elevation-Aa (West)26 Sept 2025Section Bb26 Sept 2025

Floor plans

11 files
Podium 4th Floor Plan26 Sept 2025Community Level-01 5th Floor Plan & Area Calculation26 Sept 2025Tower 2 37th to 39th & 45th to 49th Typical Floor Plan & Area Calculation26 Sept 2025

Services

Sewerage and drainage

2 files
Sewerage Assurance3 Sept 2025Storm Water Assurance3 Sept 2025

Water supply

1 file
Water Supply Assurance3 Sept 2025

Electricity

1 file
Electrical Load3 Sept 2025

Landscape and green areas

1 file
Tower 2 35th Service Floor Roof Landscape FLOOR,36TH & 40th to 44th Typical Floor & Area Calculation26 Sept 2025

Service plans

4 files
Service Plan Estimates Booklet7 Oct 2025Tower 2 17th & 26th Refuge Floor PLAN,34TH Service Floor Plan & Area Calculation26 Sept 2025Tower 1 34th Service Floor Plan, Terrace Plan & Mumty Machine Room Area Calculation26 Sept 2025Service Plans on the Layout24 Sept 2025

Approvals and clearances

Completion certificate (CC)

1 file
Section CC26 Sept 2025

DTCP licence

3 files
LOI3 Sept 2025Licence Copy with Land Schedule3 Sept 2025LC-IV3 Sept 2025

Environment clearance

1 file
Environment Clearance3 Sept 2025

Fire safety

1 file
Site Plan Fire Fighting Layout7 Oct 2025

Other NOCs and clearances

3 files
HUDA Construction Water NOC26 Sept 2025Forest NOC3 Sept 2025AAI NOC3 Sept 2025

Land records

Land records

6 files
NEC27 Nov 2025Revenue Record Entry of Licence and Collaboration26 Sept 2025Jamabandi3 Sept 2025

Money

Accounts and finance

5 files
Cash Flow Statement27 Nov 2025CA Certificate on the Application’s Figures27 Nov 2025Non-Default Certificate from a CA27 Nov 2025

The promoter’s papers

Declarations and affidavits

4 files
The Promoter’s Declaration on Affidavit6 Oct 2025Affidavit NCZ6 Oct 2025Affidavit 4(2)(L)(D)6 Oct 2025Bank Undertaking3 Sept 2025

Other filings

Other filings

2 files
Information of Revnue Deaprtment27 Nov 2025Copy of Name Change9 Oct 2025

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

141 OF 2024 · Devasya Developers Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 10 Nov 2029

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 9 Oct 2025 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

141 OF 2024

DTCP’s page showed no land schedule for licence 141 OF 2024 when Bhumiq read it on 18 Oct 2026. verify at source

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

8 files
Site Plan Road Layout7 Oct 2025Site Plan Storm Layout7 Oct 2025Site Plan Domestic Water Supply Layout7 Oct 2025Site Plan Sewerage Layout7 Oct 2025Site Plan Irrigation & Flushing Layout7 Oct 2025Superimposed Plan26 Sept 2025

Layout plan

3 files
Approved Phasing Plan26 Sept 2025Letter of Phasing Plan26 Sept 2025Latest Layout Plan24 Sept 2025

Building plans

6 files
Section Aa26 Sept 2025Elevation-Aa (West)26 Sept 2025Section Bb26 Sept 2025Tower 2 Terrace Floor Plan & Mumty Machine Area Calculation26 Sept 2025Elevation-Bb (South)26 Sept 2025Approved Building Plans, Full Set24 Sept 2025

Floor plans

11 files
Podium 4th Floor Plan26 Sept 2025Community Level-01 5th Floor Plan & Area Calculation26 Sept 2025Tower 2 37th to 39th & 45th to 49th Typical Floor Plan & Area Calculation26 Sept 2025Basement Plan26 Sept 2025Community Level-02 6th Floor Plan & Area Calculation26 Sept 2025Podium 3rd Floor Plan26 Sept 2025

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (65 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3684 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Devasya Developers Pvt. Ltd (Formerly Known As Next Generation Projects Pvt Ltd)

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.