Possession 31 Mar 2028 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 95, Gurugram5.0 km from Dwarka Expressway, in a straight line
Carpet area
386 sq ft
In m²about 36–36 m², as declared
Registered by
JMS INFRA REALITY PVT. LTD.the company that filed it, for Jms Infra Reality
Timeline
  1. 26 May 2023Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 6 Jun 2024Building plans approveddeclared to HARERA, read 29 Oct 2026
  3. 31 Mar 2028Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

2homes, 386 to 386 sq ft of carpet area
  • Under 1,000 sq ft386 sq ft2

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 2 rows of a single unit and 222 units under 25 m², because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside3,446 m² in all, by use
  • Shops and offices3,446 m² · 100%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenTile / marble / granite, paint
  • Lifts8 passanger (thyssenkrupp /johnson / OTIS or equivalent )
  • FloorsTile (vitrified and ceramic)
  • WallsCement / gypsum plaster, paint
  • BathroomsCERA / hindware or equivalent
  • WindowsAluminium frame and toghenedglass
  • Main doorFlush door
  • Electrical fittingsISI marked

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 95, GurugramSector 95, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20255.0 km
  • Delhi–Gurugram–SNB RRTS6.0 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 8 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 2
  • Registered, no OC or CC yet: 6

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is JMS GROUP CAPITAL SQUARE registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/855/587/2024/82. Valid to 31 Mar 2028.

The source ↗
What is the possession timeline for JMS GROUP CAPITAL SQUARE?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Mar 2028. Its registration runs to 31 Mar 2028; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around JMS GROUP CAPITAL SQUARE?From the records · Map pin and road lines, read 6 Sep 2026

JMS GROUP CAPITAL SQUARE is in Sector 95, Gurugram; the site address declared to HARERA is Sector 95, Village-Wazirpur. In a straight line it is about 5.0 km from Dwarka Expressway and 6.0 km from Delhi–Gurugram–SNB RRTS.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building JMS GROUP CAPITAL SQUARE?From the records · HARERA, read 4 Nov 2026

JMS GROUP CAPITAL SQUARE is a Jms Infra Reality project, registered by its company JMS INFRA REALITY PVT. LTD..

The source ↗Jms Infra Reality's projects and court record

The records

What the registers hold for JMS GROUP CAPITAL SQUARE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/855/587/2024/82: Registered. Valid to 31 Mar 2028.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 11 OF 2022 is on the DTCP register: Licence ends soon; the register prints its validity to 1 Feb 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 26 May 2023, building plans 6 Jun 2024.Declared to HARERA, read 29 Oct 2026
The court record of Jms Infra Reality’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Licence 11 OF 2022 ends soon

    Named in this project’s application. Valid to 1 Feb 2027. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 40 HARERA files, with the dates we read them
Registration no.
GGM/855/587/2024/82
Registration valid till
31 Mar 2028
Declared possession
31 Mar 2028

Declared by the promoter to HARERA

Land area
0.85 (Acre) (3,439.83 sq m)
FAR
1.75 proposed of 1.75 permissible
licence
license no 11 of 2022 dated 02.02.2022, license no 4 of 2023 dated 06.01.2023, license no 111 of 2023 dated 25.05.2023
Estimated project cost
₹41.06 crore
Cost of land
₹7.38 crore
Layout plan, declared approved (field 5a)
26 May 2023
Building plans, declared approved
6 Jun 2024
Construction to start
1 Jul 2024
Completion declared for
31 Mar 2028
Declared inventory · 34 types

Declared inventory — 34 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 1 unit · 9.59 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 2 units · 13.92 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 21 units · 14.4 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 17.4 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 18.3 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 20 units · 18.6 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 2 units · 19.5 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 6 units · 19.9 sq m carpet · under 25 m²: a shop or service unit the form does not label
Statutory approvals, as declared · 9

Statutory approvals, as declared

  • I. LICENSE- 111 OF 2023 — declared: already been obtained (25 May 2023)
  • II. LICENSE- 04 OF 2023 — declared: already been obtained (6 Jan 2023)
  • III. LICENSE- 11 OF 2022 — declared: already been obtained (2 Feb 2022)
  • IV. ZONING PLAN COMMERCIAL — declared: already been obtained (4 Mar 2024)
  • V. BUILDING PLANS BR III — declared: already been obtained (6 Jun 2024)
  • VI. LAYOUT PLAN — declared: already been obtained (26 May 2023)
  • VII. FOREST NOC — declared: already been obtained (6 Jan 2023)
  • VIII. LOI — declared: already been obtained (27 Dec 2022)
  • IX. SERVICE PLANS AND ESTIMATES — declared: already been obtained (16 Aug 2023)
On file with HARERA · 40 files

On file with HARERA (40)

Plans

Site plan

1 file
Approved Site Plan7 Jun 2024

Layout plan

2 files
Superimposed Demarcation on Layout Plan1 Aug 2024Latest Layout Plan3 May 2024

Zoning plan

2 files
Revised Approved Commercial Zonning1 Aug 2024Zoning Plan3 May 2024

Demarcation plan

1 file
Demarcation Plan1 Aug 2024

Building plans

3 files
BR-III1 Aug 2024Jms Group Capital Square Approved Plan1 Aug 2024Approved Building Plans, Full Set7 Jun 2024

Services

Sewerage and drainage

3 files
External Drainage System1 Aug 2024Storm Water, Seweage & Water Supply1 Aug 2024External Seweage System1 Aug 2024

Water supply

2 files
Domestic Water Supply Plan1 Aug 2024Recycle Water Supply1 Aug 2024

Electricity

1 file
DHBVN Load Assurance1 Aug 2024

Roads

1 file
Road Layout Plan1 Aug 2024

Service plans

2 files
Service Estimate Approval1 Aug 2024Service Plans on the Layout3 May 2024

Approvals and clearances

DTCP licence

5 files
LOI1 Aug 2024LC-IV B1 Aug 2024License-111 of 20231 Aug 2024

Fire safety

1 file
Jms Fire Approval1 Aug 2024

Other NOCs and clearances

1 file
Forest1 Aug 2024

Land records

Land records

4 files
Land Title Report1 Aug 2024Sale Deed1 Aug 2024Shizra1 Aug 2024Revenue Record Entry of Licence and Collaboration3 May 2024

Money

Accounts and finance

6 files
Cash Flow Statement1 Aug 2024Quaterly Schedule of Estimated Expenditure1 Aug 2024CA Certificate on the Application’s Figures1 Aug 2024

Timeline and progress

Construction schedule

1 file
PERT Chart1 Aug 2024

Progress and photographs

1 file
Construction Quaterly Schedule1 Aug 2024

The promoter’s papers

Declarations and affidavits

2 files
Affidavit 4(2) (L) D1 Aug 2024The Promoter’s Declaration on Affidavit1 Aug 2024

Other filings

Other filings

1 file
Wazirpur Jama., Muta., Report the Nation(jms)1 Aug 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 4 DTCP licences named on the application

11 OF 2022 · JMS Infra Reality Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 1 Feb 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

04 OF 2023 · JMS Infra Reality Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 5 Jan 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

111 OF 2023 · JMS Infra Reality Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 24 May 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

04 OF 2023 · JMS Infra Reality Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 5 Jan 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 7 Jun 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the 4 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

11 OF 2022: 25 parcels, 16.5563 acres in all, in Wazirpur (hadbast 115), tehsil Harsaru.

The licence register prints the same licensed area, 16.5563 acres.

  • 76//17/22 kanal 12 marla
  • 76//188 kanal
  • 76//197 kanal 12 marla
  • 76//20/12 kanal 6 marla
Show the other 21 parcels
  • 76//20/25 kanal 14 marla
  • 76//218 kanal
  • 76//227 kanal 12 marla
  • 76//237 kanal 15 marla
  • 76//235 marla
  • 76//248 kanal
  • 76//258 kanal
  • 77//16/13 kanal 15 marla
  • 77//254 kanal 10 marla
  • 78//5/12 kanal
  • 79//1/12 kanal 9 marla
  • 79//13/114 marla
  • 79//14/31 kanal 16 marla
  • 79//17/1/11 kanal 3 marla
  • 79//2/12 kanal 6 marla
  • 79//38 kanal
  • 79//48 kanal
  • 79//58 kanal
  • 79//68 kanal
  • 79//78 kanal
  • 79//88 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

04 OF 2023: 5 parcels, 2.4563 acres in all, in Wazirpur (hadbast 115), tehsil Harsaru.

The licence register prints the same licensed area, 2.4563 acres.

  • 78//5/23 kanal 12 marla
  • 79//1/25 kanal 11 marla
  • 79//10/11 kanal 7 marla
  • 79//2/25 kanal 6 marla
Show the other 1 parcel
  • 79//9/13 kanal 17 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

111 OF 2023: 6 parcels, 3.3438 acres in all, in Wazirpur (hadbast 115), tehsil Harsaru.

The licence register prints the same licensed area, 3.3438 acres.

  • 79//13/217 marla
  • 79//13/36 kanal 9 marla
  • 79//14/11 kanal 11 marla
  • 79//14/24 kanal 13 marla
Show the other 2 parcels
  • 79//17/1/25 kanal 5 marla
  • 79//188 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

04 OF 2023: 5 parcels, 2.4563 acres in all, in Wazirpur (hadbast 115), tehsil Harsaru.

The licence register prints the same licensed area, 2.4563 acres.

  • 78//5/23 kanal 12 marla
  • 79//1/25 kanal 11 marla
  • 79//10/11 kanal 7 marla
  • 79//2/25 kanal 6 marla
Show the other 1 parcel
  • 79//9/13 kanal 17 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Wazirpur (hadbast 115), tehsil Harsaru. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 76//17/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan7 Jun 2024

Layout plan

2 files
Superimposed Demarcation on Layout Plan1 Aug 2024Latest Layout Plan3 May 2024

Building plans

3 files
BR-III1 Aug 2024Jms Group Capital Square Approved Plan1 Aug 2024Approved Building Plans, Full Set7 Jun 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (40 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2914 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Jms Infra Reality

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.