Skip to content

ORCHARD AVENUE - 3

by Signature Builders · Sector 93, Gurugram

Not on our price list yet

Possession 31 Jul 2028 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 93, Gurugram3.1 km from Dwarka Expressway, in a straight line
Carpet area
541–2,456 sq ft
In m²about 50–228 m², as declared
Registered by
SIGNATURE BUILDERS PRIVATE LIMITEDthe company that filed it, for Signature Builders
Timeline
  1. 31 Jan 2024Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Jul 2028Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

253homes, 541 to 2,456 sq ft of carpet area
  • Under 1,000 sq ft541–640 sq ft235
  • 2,000–2,500 sq ft2,456 sq ft18

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside1.663 acres in all, by use
  • Roads0.669 acres · 40%
  • Parking0.306 acres · 18%
  • Apartment buildings0.304 acres · 18%
  • Parks and playgrounds0.286 acres · 17%
  • Land for community services, handed to the government0.05 acres · 3%
  • Other usesas the form names them: Commercial area0.048 acres · 3%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenISI marked
  • Kitchen appliancesISI marked
  • LiftsISI marked
  • FloorsVitrified & ceramic tiles
  • WallsOBD
  • BathroomsISI marked
  • WindowsAluminiumn/UPVC
  • Main doorFlush door

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 93, GurugramSector 93, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20253.1 km
  • Delhi–Gurugram–SNB RRTS4.8 km
  • Sohna Elevated Corridor (NH-248A)10.3 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 7 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 4
  • Registered, no OC or CC yet: 3

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is ORCHARD AVENUE - 3 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/789/521/2024/16. Valid to 31 Jul 2028.

The source ↗
What is the possession timeline for ORCHARD AVENUE - 3?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Jul 2028. Its registration runs to 31 Jul 2028; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ORCHARD AVENUE - 3?From the records · Map pin and road lines, read 6 Sep 2026

ORCHARD AVENUE - 3 is in Sector 93, Gurugram; the site address declared to HARERA is Village - Hayatpur, Sector -93, Gurugram, Haryana. In a straight line it is about 3.1 km from Dwarka Expressway, 4.8 km from Delhi–Gurugram–SNB RRTS and 10.3 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ORCHARD AVENUE - 3?From the records · HARERA, read 4 Nov 2026

ORCHARD AVENUE - 3 is a Signature Builders project, registered by its company SIGNATURE BUILDERS PRIVATE LIMITED.

The source ↗Signature Builders's projects and court record

The records

What the registers hold for ORCHARD AVENUE - 3: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/789/521/2024/16: Registered. Valid to 31 Jul 2028.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 162 OF 2023 is on the DTCP register, valid to 10 Aug 2028.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 31 Jan 2024.Declared to HARERA, read 29 Oct 2026
The court record of Signature Builders’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 36 HARERA files, with the dates we read them
Registration no.
GGM/789/521/2024/16
Registration valid till
31 Jul 2028
Declared possession
31 Jul 2028

Declared by the promoter to HARERA

Land area
1.6625 (Acre) (6,727.9 sq m)
FAR
2.27 proposed of 2.28 permissible
licence
162 OF 2023 Dated 11-08-2023
Estimated project cost
₹67.28 crore
Cost of land
₹9.17 crore
Building plans, declared approved
31 Jan 2024
Construction to start
1 Jan 2024
Completion declared for
31 Jul 2028
Declared inventory · 6 types

Declared inventory

  • Apartment/Shops/Other Buildings · 58 units · 50.244 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 56 units · 56.325 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 56 units · 58.293 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 58 units · 53.531 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 7 units · 59.419 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 18 units · 228.178 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. LICENSE NO. 162 OF 2023 — declared: already been obtained (11 Aug 2023)
  • II. FOREST NOC — declared: already been obtained (20 Dec 2021)
  • III. AAI NOC — declared: already been obtained (14 Sept 2023)
  • IV. BR-III — declared: already been obtained (31 Jan 2024)
On file with HARERA · 36 files

On file with HARERA (36)

Plans

Site plan

2 files
Site Plan5 Jun 2024Approved Site Plan5 Jun 2024

Layout plan

1 file
Latest Layout Plan31 Jan 2024

Zoning plan

1 file
Zoning Plan5 Jun 2024

Demarcation plan

2 files
Superimposed Demarcation5 Jun 2024Demarcation Plan31 Jan 2024

Building plans

19 files
Approved Building Plan Oa-3-115 Jun 2024Approved Building Plan Oa-3-135 Jun 2024Approved Building Plan Oa-3-185 Jun 2024

Services

Service plans

2 files
Manged Service Estimates and Plans5 Jun 2024Service Plans on the Layout31 Jan 2024

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule5 Jun 2024

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration5 Jun 2024

Money

Accounts and finance

5 files
Cash Flow Statement5 Jun 2024CA Certificate for Cost Incurred5 Jun 2024Land Cost CA Certificate5 Jun 2024

The promoter’s papers

Declarations and affidavits

2 files
Promoter Affidavit5 Jun 2024The Promoter’s Declaration on Affidavit5 Jun 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

162 OF 2023 · SIGNATURE BUILDERS PVT. LTD. · GURGAON-MANESAR

Licence valid to 10 Aug 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 2 Feb 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

162 OF 2023: 5 parcels, 1.6625 acres in all, in Hayatpur (hadbast 114), tehsil Harsaru.

The licence register prints the same licensed area, 1.6625 acres.

  • 37//25/41 kanal 9 marla
  • 38//21/35 kanal 18 marla
  • 39//1min3 kanal 15 marla
  • 39//26min5 marla
Show the other 1 parcel
  • 40//5/4min1 kanal 19 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Hayatpur (hadbast 114), tehsil Harsaru. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 37//25/4.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Site Plan5 Jun 2024Approved Site Plan5 Jun 2024

Layout plan

1 file
Latest Layout Plan31 Jan 2024

Building plans

19 files
Approved Building Plan Oa-3-115 Jun 2024Approved Building Plan Oa-3-135 Jun 2024Approved Building Plan Oa-3-185 Jun 2024Approved Building Plan Oa-3-165 Jun 2024Approved Building Plan Oa-3-155 Jun 2024Approved Building Plan Oa-3-85 Jun 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (36 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2679 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Signature Builders

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.