About this project

Key facts

Location
Sector 90, Gurugram3.0 km from Dwarka Expressway, in a straight linePrices and what changed
Carpet area
1,485 sq ft
In m²about 138–138 m², as declared
Asking rate
₹14,000 a sq ft of carpet
Bhumiq team price list, 16 Sep 2026
Registered by
NORTH STAR TOWERS PRIVATE LIMITEDthe company that filed it, for SS Group
Timeline
  1. 12 Aug 2024Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Sep 2031Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

512homes, 1,485 to 1,485 sq ft of carpet area
  • 1,000–1,500 sq ft1,485 sq ft512

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.046 acres in all, by use
  • Parks and playgrounds1.8 acres · 36%
  • Roads1.745 acres · 35%
  • Apartment buildings0.739 acres · 15%
  • Shops and offices0.35 acres · 7%
  • Parking0.312 acres · 6%
  • Other usesas the form names them: EWS (homes for economically weaker sections)0.1 acres · 2%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningSplit AIR-conditioners in living room and bed rooms
  • KitchenStone counter with single lever CP fittings and sink
  • Kitchen appliancesShall not be provided by promoter
  • LiftsEach tower has BEEN provided 03 NOS passanger lifts and 01 service lift
  • WardrobesModular wardrobes shall not be provided by promoter
  • FloorsVitrified tile
  • WallsOil bound distemper
  • BathroomsStone counter top with single lever CP fittings ,WASH basin, wall hung WC

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 90, GurugramSector 90, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20253.0 km
  • Delhi–Gurugram–SNB RRTS3.8 km
  • Sohna Elevated Corridor (NH-248A)10.1 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 14 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 5
  • Registered, no OC or CC yet: 5
  • Other register states: 4

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is SS Camasa registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/881/613/2024/108. Valid to 30 Sep 2031.

The source ↗
What is the possession timeline for SS Camasa?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Sep 2031. Its registration runs to 30 Sep 2031; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around SS Camasa?From the records · Map pin and road lines, read 6 Sep 2026

SS Camasa is in Sector 90, Gurugram; the site address declared to HARERA is Sector 90, Village Badha & Nawada Fatehpur. In a straight line it is about 3.0 km from Dwarka Expressway, 3.8 km from Delhi–Gurugram–SNB RRTS and 10.1 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What does a home in SS Camasa cost, and how does that compare nearby?From the records · Bhumiq team price list, 16 Sep 2026

The Bhumiq team's price list has ₹14,000 a sq ft of carpet area (16 Sep 2026). Prices change; ask the developer for its current price list.

What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty

The records

What the registers hold for SS Camasa: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/881/613/2024/108: Registered. Valid to 30 Sep 2031.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 265 OF 2023 is on the DTCP register, valid to 18 Dec 2028.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 12 Aug 2024, building plans 12 Aug 2024.Declared to HARERA, read 29 Oct 2026
The court record of SS Group’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 63 HARERA files, with the dates we read them
Registration no.
GGM/881/613/2024/108
Registration valid till
30 Sept 2031
Declared possession
30 Sept 2031
Asking price (indicative)
₹14,000 / sq ft of carpet area

Bhumiq team price list · as of 16 Sept 2026 · a quoted rate, not a registry figure

Declared by the promoter to HARERA

Land area
5.0456 (Acre) (20,418.82 sq m)
FAR
3.48 proposed of 3.62 permissible
licence
265 of 2023(19-12-2023)
Estimated project cost
₹638.27 crore
Cost of land
₹14.01 crore
Layout plan, declared approved (field 5a)
12 Aug 2024
Building plans, declared approved
12 Aug 2024
Construction to start
1 Dec 2024
Completion declared for
30 Sept 2031
Declared inventory · 1 type

Declared inventory

  • Apartment/Shops/Other Buildings · 512 units · 137.95 sq m carpet · 4 towers · one flat
Statutory approvals, as declared · 5

Statutory approvals, as declared

  • I. BUILDING PLAN — declared: already been obtained (12 Aug 2024)
  • II. ZONING PLAN — declared: already been obtained (5 Jun 2024)
  • III. LICENSE FROM TOWN & COUNTRY PLANNING HARYANA — declared: already been obtained (19 Dec 2023)
  • IV. PHASING PLAN APPROVAL — declared: already been obtained (17 Jul 2024)
  • V. FIRE SCHEME APPROVAL — declared: already been obtained (17 Oct 2024)
On file with HARERA · 63 files

On file with HARERA (63)

Plans

Site plan

4 files
Site Plan Green Area Calculation10 Feb 2025Approved Site Plan10 Feb 2025Site Plan - Layout Plan10 Feb 2025Site Plan-Phasing Plan21 Aug 2024

Layout plan

3 files
Phasing Plan - Plan Approval10 Feb 2025Phasing Plan - Approval Letter10 Feb 2025Latest Layout Plan21 Aug 2024

Zoning plan

2 files
Revised Zoning Plan10 Feb 2025Zoning Plan10 Feb 2025

Demarcation plan

1 file
Demarcation Plan10 Feb 2025

Building plans

10 files
Elevation B & D10 Feb 2025Section 1 & 210 Feb 2025Terrace Floor Plan EWS10 Feb 2025

Floor plans

13 files
Basement Plan-0210 Feb 2025Typical Floor Plan 01 to 32 (Except 19 & 28) T-1 to T-410 Feb 2025Second Floor Area Plan10 Feb 2025

Services

Sewerage and drainage

1 file
Assurance - Sewerage Connection10 Feb 2025

Water supply

3 files
Water Supply Schematic Diagram10 Feb 2025Assurance - Drinking Water10 Feb 2025Assurance - Construction Water10 Feb 2025

Electricity

1 file
Assurance - Electric Load10 Feb 2025

Roads

1 file
Road Access Approval Letter10 Feb 2025

Service plans

1 file
Service Plans on the Layout17 Aug 2024

Approvals and clearances

DTCP licence

3 files
Licence Copy with Land Schedule10 Feb 2025LC-IV10 Feb 2025LOI10 Feb 2025

Other NOCs and clearances

1 file
NOC - AAI - Airport Height10 Feb 2025

Land records

Land records

4 files
Ak Sizra10 Feb 2025TSR Camasa10 Feb 2025Collaboration10 Feb 2025Revenue Record Entry of Licence and Collaboration10 Feb 2025

Sales papers

Allotment and sale agreements

2 files
Draft Agreement for Sale - Ss Camasa10 Feb 2025Draft Allotment Letter - Ss Camasa10 Feb 2025

Money

Accounts and finance

7 files
Non-Default Certificate from a CA10 Feb 2025Cash Flow Statement10 Feb 2025Project Report of Ss Camasa10 Feb 2025

The promoter’s papers

Declarations and affidavits

3 files
Affidavit - Tree Power Natural Conservation10 Feb 2025The Promoter’s Declaration on Affidavit10 Feb 2025Draft Application Form- Ss Camasa10 Feb 2025

Other filings

Other filings

3 files
Courtyard Area Detail10 Feb 2025Elvation A & B Community10 Feb 2025Elvation C & D Community10 Feb 2025

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

265 OF 2023 · Northstar Towers Pvt Ltd · GURGAON-MANESAR

Licence valid to 18 Dec 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 21 Aug 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

265 OF 2023

DTCP’s page showed no land schedule for licence 265 OF 2023 when Bhumiq read it on 18 Oct 2026. verify at source

Collector rate, residential flat
₹7,000 per sq ft

Sector 90, collector rates effective 1 Apr 2026, Harsaru tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

4 files
Site Plan Green Area Calculation10 Feb 2025Approved Site Plan10 Feb 2025Site Plan - Layout Plan10 Feb 2025Site Plan-Phasing Plan21 Aug 2024

Layout plan

3 files
Phasing Plan - Plan Approval10 Feb 2025Phasing Plan - Approval Letter10 Feb 2025Latest Layout Plan21 Aug 2024

Building plans

10 files
Elevation B & D10 Feb 2025Section 1 & 210 Feb 2025Terrace Floor Plan EWS10 Feb 2025Elevation A & C10 Feb 2025BR-III10 Feb 2025Section Community10 Feb 2025

Floor plans

13 files
Basement Plan-0210 Feb 2025Typical Floor Plan 01 to 32 (Except 19 & 28) T-1 to T-410 Feb 2025Second Floor Area Plan10 Feb 202519th & 28th Floor Plan10 Feb 2025Stilt Floor Plan EWS10 Feb 2025Stilt Floor Plan T-310 Feb 2025

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (63 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3070 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on SS Group

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.