THE EMPIRE CENTRE
by Essel Infra · Sector 43, Gurugram
Not on our price list yet
Possession 31 Jan 2030 · as the developer declared it to HARERA
About this project
Key facts
- Location
- Sector 43, Gurugram3.2 km from Delhi–Gurugram–SNB RRTS, in a straight line
- Registered by
- ESSEL INFRA LLPthe company that filed it, for Essel Infra
- 27 Sep 2024Building plans approveddeclared to HARERA, read 29 Oct 2026
- 31 Jan 2030Possession, as declareddeclared to HARERA, read 29 Oct 2026
Homes on offer
The homes the developer declared to HARERA, by size.
- Under 1,000 sq ft270–408 sq ft75
- 2,500–3,000 sq ft2,733–2,929 sq ft26
Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 16 rows of a single unit and 51 units under 25 m², because the form lists homes, shops and other buildings in one table.
Amenities and specifications
How the land is set aside and what comes in each home, as the developer declared them to HARERA.
- Apartment buildings1,871 m² · 60%
- Pavements1,249 m² · 40%
The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.
- Air-conditioningVRV/ water cooler chiller
- KitchenVitrified tiles
- Lifts6 lift , 9/15 passenger / ottis, fujitech,T.K. elevators ETC
- FloorsVitrified tiles
- WallsGlazed ceramic tiles/ paint /OBD
- BathroomsHindware, CERA, parry WARE
- WindowsAluminum frame with glass
- Main doorPRE-laminated flush door/hdhmr door
The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
- Delhi–Gurugram–SNB RRTS3.2 km
- Sohna Elevated Corridor (NH-248A)5.2 km
- Dwarka ExpresswayOpen, 17 Aug 20259.2 km
Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.
Map data © OpenStreetMap contributors.
The builder
- OC or CC dispatched: 1
- Registered, no OC or CC yet: 2
Other projects nearby
8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.
| Project | Builder | Distance | Stage | Asking rate | Possession |
|---|---|---|---|---|---|
THE EMPIRENo photo on file yet | Essel Infra | Same sector | — | — | 21 Aug 2028 |
Plot No GH-24No photo on file yet | The Bajrang Co-operative Group Housing Society | Same sector | — | — | — |
| Godrej Highview | Same sector | Under construction | ₹26,000/sq ft | 30 Sep 2031 | |
| DLF | 1.1 kmto its sector’s point | — | — | 15 May 2025 | |
| Godrej Highview | 1.9 kmto its sector’s point | New launch | ₹28,000/sq ft | 30 Sep 2032 | |
No photo of the project on file yet | Tulip Infratech | 1.9 kmto its sector’s point | Under construction | — | 17 May 2022 |
DALCORE THE FALCONNo photo on file yet | Ahir Infraspace | 1.9 kmto its sector’s point | — | — | 31 Mar 2031 |
| Godrej Highview | 1.9 kmto its sector’s point | New launch | ₹31,000/sq ft | 31 Aug 2033 |
Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.
Questions buyers ask
Is THE EMPIRE CENTRE registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as GGM/919/651/2025/22. Valid to 31 Jan 2030.
The source ↗What is the possession timeline for THE EMPIRE CENTRE?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 31 Jan 2030. Its registration runs to 31 Jan 2030; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around THE EMPIRE CENTRE?From the records · Map pin and road lines, read 6 Sep 2026
THE EMPIRE CENTRE is in Sector 43, Gurugram; the site address declared to HARERA is Commercial Complex , Plot No. C2, Sector 43, Gurugram. In a straight line it is about 3.2 km from Delhi–Gurugram–SNB RRTS, 5.2 km from Sohna Elevated Corridor (NH-248A) and 9.2 km from Dwarka Expressway.
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building THE EMPIRE CENTRE?From the records · HARERA, read 4 Nov 2026
THE EMPIRE CENTRE is a Essel Infra project, registered by its company ESSEL INFRA LLP.
The source ↗Essel Infra's projects and court recordThe records
What the registers hold for THE EMPIRE CENTRE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration GGM/919/651/2025/22: Registered. Valid to 31 Jan 2030.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Plans approved, as the developer declared: building plans 27 Sep 2024.Declared to HARERA, read 29 Oct 2026
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 43 HARERA files, with the dates we read them
- Registration no.
- GGM/919/651/2025/22
- Registration valid till
- 31 Jan 2030
- Declared possession
- 31 Jan 2030
Declared by the promoter to HARERA
- Land area
- 0.7710 (Acre) (3,120.13 sq m)
- FAR
- 5.12 proposed of 5.12 permissible
- licence
- HSVP AllottedCommercial PlotNo. C2, Sector 43,GurugramAllotment Letterno. ZO002/EO018/UE029/GALOT/0000000649dated14.07.2022
- Estimated project cost
- ₹359.89 crore
- Cost of land
- ₹133.77 crore
- Building plans, declared approved
- 27 Sept 2024
- Construction to start
- 1 Feb 2025
- Completion declared for
- 31 Jan 2030
Declared inventory · 82 types
Declared inventory — 82 types declared, first 8 shown
- Apartment/Shops/Other Buildings · 1 unit · 3.96 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 3 units · 5.16 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 2 units · 5.22 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 2 units · 9.72 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 6 units · 14.12 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 1 unit · 14.26 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 1 unit · 14.3 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 2 units · 14.39 sq m carpet · 1 tower · under 25 m²: a shop or service unit the form does not label
Statutory approvals, as declared · 10
Statutory approvals, as declared
- I. ALLOTMENT LETTER FROM HSVP — declared: already been obtained (14 Jul 2022)
- II. POSSESSION LETTER FROM HSVP — declared: already been obtained (19 Jul 2022)
- III. HEIGHT NOC — declared: already been obtained (20 Oct 2022)
- IV. FOREST NOC — declared: already been obtained (20 Oct 2022)
- V. BUILDING PLAN — declared: already been obtained (27 Sept 2024)
- VI. MINING PERMISSION — declared: already been obtained (2 Feb 2025)
- VII. ELECTRICAL POWER LOAD ASSURANCE — declared: already been obtained (7 Aug 2023)
- VIII. ENVIRONMENT CLERANCE — declared: already been obtained (31 Jan 2025)
- IX. CONSENT TO ESTABLISH — declared: already been obtained (10 Feb 2025)
- X. CONVEYANCE DEED — declared: already been obtained (18 Nov 2024)
On file with HARERA · 43 files
On file with HARERA (43)
Plans
Site plan
2 filesLayout plan
1 fileZoning plan
2 filesDemarcation plan
1 fileBuilding plans
5 filesFloor plans
2 filesServices
Sewerage and drainage
1 fileElectricity
1 fileApprovals and clearances
DTCP licence
2 filesEnvironment clearance
1 fileFire safety
1 fileOther NOCs and clearances
7 filesLand records
Land records
3 filesSales papers
Allotment and sale agreements
3 filesMoney
Accounts and finance
7 filesThe promoter’s papers
Declarations and affidavits
4 filesThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
The promoter declared HSVP AllottedCommercial PlotNo. C2, Sector 43,GurugramAllotment Letterno. ZO002/EO018/UE029/GALOT/0000000649dated14.07.2022. We could not read a licence number from that, so nothing is claimed about it here.
declared in the registration application (Form REP-I), Gurugram bench · submitted 24 Dec 2024 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026
Collector rate
No one collector rate can be matched to this project's type.
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
2 filesLayout plan
1 fileBuilding plans
5 filesFloor plans
2 filesAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (43 in all), none is a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/3195 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Essel Infra
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.