Skip to content

ARDEN 45

by Uday Buildwell · Sector 45, Gurugram

Not on our price list yet

About this project

Key facts

Location
Sector 45, Gurugram2.4 km from Delhi–Gurugram–SNB RRTS, in a straight line
Registered by
UDAY BUILDLWELL PRIVATE LIMITEDthe company that filed it, for Uday Buildwell
Timeline
  1. 12 Jan 2024Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Oct 2026Registration valid toHARERA, read 4 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside1.025 acres in all, by use
  • Apartment buildings0.518 acres · 51%
  • Roads0.492 acres · 48%
  • Parks and playgrounds0.01 acres · under 1%
  • Electricity sub-station0.005 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningVRV system/centralized chilled water system or as per consultant
  • LiftsOTIS/KONE/ ECE/FUJI TECH/equivalent
  • WindowsAlpro, nayur door KING, bhutantuff, jyoti or equivalent
  • Main doorAlpro, nayur door KING, bhutantuff, jyoti or equivalent
  • Electrical fittingsPolypack, apter, ATUL or equivalent anchor, ABB or equivalent

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 45, GurugramSector 45, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Delhi–Gurugram–SNB RRTS2.4 km
  • Sohna Elevated Corridor (NH-248A)3.1 km
  • Dwarka ExpresswayOpen, 17 Aug 20258.4 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 2

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is ARDEN 45 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/817/549/2024/44. Ended 31 Oct 2026. The register shows it as: Registration expired.

The source ↗
How is the connectivity around ARDEN 45?From the records · Map pin and road lines, read 6 Sep 2026

ARDEN 45 is in Sector 45, Gurugram; the site address declared to HARERA is Village Kanhai, Sector-45. In a straight line it is about 2.4 km from Delhi–Gurugram–SNB RRTS, 3.1 km from Sohna Elevated Corridor (NH-248A) and 8.4 km from Dwarka Expressway.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ARDEN 45?From the records · HARERA, read 4 Nov 2026

ARDEN 45 is a Uday Buildwell project, registered by its company UDAY BUILDLWELL PRIVATE LIMITED.

The source ↗Uday Buildwell's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for ARDEN 45: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/817/549/2024/44: Registration expired. Ended 31 Oct 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 204 OF 2022 is on the DTCP register, valid to 12 Dec 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 12 Jan 2024, building plans 12 Jan 2024.Declared to HARERA, read 29 Oct 2026
The court record of Uday Buildwell’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 31 Oct 2026. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 31 HARERA files, with the dates we read them
Registration no.
GGM/817/549/2024/44
Registration valid till
31 Oct 2026

Declared by the promoter to HARERA

Land area
1.025 (Acre) (4,148.03 sq m)
FAR
1.87 proposed of 1.87 permissible
licence
204 OF 2022 for 0.65 Acres and 189 of 2023 for 0.375 Acres
Estimated project cost
₹226.66 crore
Cost of land
₹110.96 crore
Layout plan, declared approved (field 5a)
12 Jan 2024
Building plans, declared approved
12 Jan 2024
Declared inventory · 1 type

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP · 279 units
Statutory approvals, as declared · 6

Statutory approvals, as declared

  • I. LICENCE 204/2022 — declared: already been obtained (13 Dec 2022)
  • II. LICENCE 189/2023 — declared: already been obtained (15 Sept 2023)
  • III. REVISED BUILDING PLAN BR III — declared: already been obtained (12 Jan 2024)
  • IV. REVISED ZONING PLAN — declared: already been obtained (15 Sept 2023)
  • V. REVISED SERVICE PLAN — declared: already been obtained (7 Feb 2024)
  • VI. REVISED FIRE SCHEME — declared: already been obtained (23 Feb 2024)
On file with HARERA · 31 files

On file with HARERA (31)

Plans

Site plan

2 files
Superimposed Plan13 Jun 2024Approved Site Plan4 Jan 2024

Layout plan

1 file
Latest Layout Plan4 Jan 2024

Zoning plan

1 file
Zoning Plan4 Jan 2024

Demarcation plan

1 file
Demarcation Plan4 Jan 2024

Building plans

2 files
Approved Building Plans, Full Set13 Jun 2024Elevation and Section13 Jun 2024

Floor plans

5 files
Basement 1 Plan13 Jun 2024Fourth Floor Plan13 Jun 2024Typical First to Third Floor13 Jun 2024

Services

Sewerage and drainage

2 files
Storm Water Drainage Plan13 Jun 2024Sewerage Plan13 Jun 2024

Water supply

1 file
Water Supply Plan13 Jun 2024

Roads

1 file
Road and Pavment Plan13 Jun 2024

Landscape and green areas

1 file
Landscape Plan13 Jun 2024

Service plans

1 file
Service Plans on the Layout13 Jun 2024

Approvals and clearances

DTCP licence

2 files
License 204 of 202213 Jun 2024Licence Copy with Land Schedule4 Jan 2024

Fire safety

1 file
Fire Scheme Approval13 Jun 2024

Land records

Land records

6 files
NEC18 Jun 2024Jamabandi Current Arden13 Jun 2024Aks Shijra Arden13 Jun 2024

Money

Accounts and finance

2 files
Non-Default Certificate from a CA4 Jan 2024Cash Flow Statement4 Jan 2024

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit4 Jan 2024

Other filings

Other filings

1 file
NEC213 Jun 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

204 OF 2022 · Uday Buildwell Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 12 Dec 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

189 OF 2023 · Uday Buildwell Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 14 Sept 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 4 Jan 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the 2 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

204 OF 2022: 8 parcels, 0.65 acres in all, in Kanehi (hadbast 73), tehsil Wazirabad.

The licence register prints the same licensed area, 0.65 acres.

  • 36//16/23 marla
  • 36//16/31 marla
  • 36//25/2/1/1/31 kanal 2 marla
  • 36//25/2/1/31 kanal 2 marla
Show the other 4 parcels
  • 36//25/2/1/410 marla
  • 36//25/2/22 kanal
  • rectangle 36, kila 98/24 marla
  • rectangle 36, kila 98/32 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

189 OF 2023: 1 parcel, 0.375 acres in all, in Kanehi (hadbast 73), tehsil Wazirabad.

The licence register prints the same licensed area, 0.375 acres.

  • 37//21/23 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Kanehi (hadbast 73), tehsil Wazirabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 36//16/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Superimposed Plan13 Jun 2024Approved Site Plan4 Jan 2024

Layout plan

1 file
Latest Layout Plan4 Jan 2024

Building plans

2 files
Approved Building Plans, Full Set13 Jun 2024Elevation and Section13 Jun 2024

Floor plans

5 files
Basement 1 Plan13 Jun 2024Fourth Floor Plan13 Jun 2024Typical First to Third Floor13 Jun 2024Basement-2 Plan13 Jun 2024Ground Floor Plan13 Jun 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (31 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2742 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Uday Buildwell

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.