About this project

Key facts

Location
Sector 104, Gurugram0.6 km from Dwarka Expressway, in a straight linePrices and what changed
Home types
1, 3 and 4 BHK
Carpet area
978–2,700 sq ft
In m²about 91–251 m², as declared
Registered
21 Aug 2017
Registered by
GODREJ PROJECTS DEVELOPMENT LIMITEDthe company that filed it, for Godrej Projects Development
Timeline
  1. 21 Aug 2017Registered with HARERAHARERA, read 4 Nov 2026
  2. 30 Sep 2018Registration valid toHARERA, read 4 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

175homes, 978 to 2,700 sq ft of carpet area
  • Under 1,000 sq ft978 sq ft17
  • 1,000–1,500 sq ft1,044–1,330 sq ft124
  • 1,500–2,000 sq ft1,541 sq ft32
  • 2,500–3,000 sq ft2,700 sq ft2

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 4 rows of a single unit and 2 units under 25 m², because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

In each home
  • KitchenGranite counter with sink and CP fittings
  • LiftsYes
  • WardrobesNo wardrobe
  • FloorsVitrified tile or EQV. in living/dining, wooden flooring or EQV. in bedrooms, anti-skid tiles or EQV. in toilets, kitchen, balcony & utility
  • WallsAcrylic emulsion or EQV. in intenal walls, oil bound distemper or EQV. in ceiling, weather proof or EQV. in external
  • BathroomsYes - CP/sanitary
  • WindowsAluminium
  • Main doorModuled shutter in TEAK finish with TEAK wood frame

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 104, GurugramSector 104, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.6 km
  • Delhi–Gurugram–SNB RRTS4.6 km
  • Sohna Elevated Corridor (NH-248A)5.5 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 4 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Registered, no OC or CC yet: 2
  • Other register states: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is Godrej Summit registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 75 OF 2017, registered on 21 Aug 2017. Ended 30 Sep 2018. The register shows it as: Registration expired.

The source ↗
How is the connectivity around Godrej Summit?From the records · Map pin and road lines, read 6 Sep 2026

Godrej Summit is in Sector 104, Gurugram; the site address declared to HARERA is Sector 104. In a straight line it is about 0.6 km from Dwarka Expressway, 4.6 km from Delhi–Gurugram–SNB RRTS and 5.5 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Godrej Summit?From the records · HARERA, read 4 Nov 2026

Godrej Summit is a Godrej Projects Development project, registered by its company GODREJ PROJECTS DEVELOPMENT LIMITED.

The source ↗Godrej Projects Development's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for Godrej Summit: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 75 OF 2017: Registration expired. Ended 30 Sep 2018.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 102 OF 2011 is on the DTCP register, valid to 6 Dec 2029.DTCP, read 3 Nov 2026
The court record of Godrej Projects Development’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 30 Sep 2018. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 41 HARERA files, with the dates we read them
Registration no.
75 OF 2017
Registration date
21 Aug 2017
Registration valid till
30 Sept 2018

Declared by the promoter to HARERA

Land area
2.0130 (Acre) (8,146.32 sq m)
FAR
1.75 proposed of 1.75 permissible
licence
Licence No 102 of 2011 dated 07.12.2011
Estimated project cost
₹141.62 crore
Declared inventory · 14 types

Declared inventory — 14 types declared, first 8 shown

  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK TYPE-II · 17 units · 90.84 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK + UTILITY TYPE I · 72 units · 97.34 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK + UTILITY TYPE II · 18 units · 96.95 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 4 BHK+ UTILITY · 34 units · 123.57 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 4 BHK + 4 TOI+ STUDY+ UTILITY · 32 units · 143.18 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type PENT HOUSE · 2 units · 250.88 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type NON STANDARD-1BHK (TOWER-L) TYPE-1 · 1 unit · 46.64 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type NON STANDARD-1BHK (TOWER-L) TYPE-2 · 1 unit · 38.91 sq m carpet · one flat
Statutory approvals, as declared · 27

Statutory approvals, as declared

  • I. LICENCE — declared: already been obtained (7 Dec 2011)
  • II. RENEWAL OF LICENCE — declared: already been obtained (10 Feb 2020)
  • III. CHANGE OF DEVELOPER — declared: already been obtained (25 Jan 2018)
  • IV. ZONING PLAN — declared: already been obtained (8 Dec 2011)
  • V. AAI — declared: already been obtained (30 Jan 2012)
  • VI. RENEWAL OF AAI — declared: already been obtained (14 Dec 2017)
  • VII. NOC FOR CONSTRUCTION ACTIVITY — declared: already been obtained (3 Oct 2012)
  • VIII. BUILDING PLAN — declared: already been obtained (5 Sept 2012)
  • IX. PERMISSION FOR MINING — declared: already been obtained (13 Mar 2013)
  • X. EXTENSION OF MINING PERMISSION — declared: already been obtained (11 Nov 2014)
  • XI. FOREST NOC — declared: already been obtained (24 Apr 2012)
  • XII. ENVIRONMENT CLEARANCE — declared: already been obtained (4 Sept 2013)
  • XIII. CONSENT TO ESTABLISH — declared: already been obtained (9 Oct 2013)
  • XIV. EXTENSION OF VALIDITY PERIOD OF CTE — declared: already been obtained (2 Nov 2016)
  • XV. FIRE SCHEME — declared: already been obtained (21 Jan 2013)
  • XVI. ELECTRICAL LOAD — declared: already been obtained (31 Mar 2015)
  • XVII. SERVICE PLAN ESTIMATES — declared: already been obtained (19 Jan 2015)
  • XVIII. FIRE NOC, PHASE I — declared: already been obtained (9 Jan 2017)
  • XIX. FIRE NOC, PHASE II — declared: already been obtained (26 May 2017)
  • XX. FIRE NOC, PHASE III — declared: already been obtained (18 May 2018)
  • XXI. WATER PERMISSION — declared: already been obtained (20 Nov 2017)
  • XXII. SEWERAGE PERMISSION — declared: already been obtained (17 Jul 2018)
  • XXIII. STORM WATER CONNECTION — declared: already been obtained (6 Jul 2018)
  • XXIV. OCCUPATION CERTIFICATE, PHASE I — declared: already been obtained (7 Apr 2017)
  • XXV. OCCUPATION CERTIFICATE, PHASE II — declared: already been obtained (20 Jun 2017)
  • XXVI. OCCUPATION CERTIFICATE, PHASE III — declared: already been obtained (26 Dec 2018)
  • XXVII. CONSENT TO OPERATE — declared: already been obtained (11 Jul 2017)
On file with HARERA · 41 files

On file with HARERA (41)

Plans

Site plan

1 file
Approved Site Plan25 Feb 2020

Layout plan

1 file
Latest Layout Plan26 Feb 2020

Zoning plan

1 file
Zoning Plan25 Feb 2020

Demarcation plan

1 file
Demarcation Plan26 Feb 2020

Building plans

2 files
Approved Building Plans, Full Set26 Feb 2020Approval of Building Plan25 Feb 2020

Services

Sewerage and drainage

2 files
Approval of Sewerage25 Feb 2020Approval of Storm Water Connection25 Feb 2020

Water supply

1 file
Approval of Water Supply for Domestic Purpose25 Feb 2020

Electricity

1 file
Approval of Electric Load Connection25 Feb 2020

Service plans

3 files
Service Plans on the Layout25 Feb 2020Approval of Service Plan Estimates25 Feb 2020Service Plan Estimate Report25 Feb 2020

Approvals and clearances

Occupation certificate (OC)

4 files
OC uploaded4 Aug 2023Occupation Certificate, Phase III25 Feb 2020Occupation Certificate, Phase I25 Feb 2020Occupation Certificate, Phase II25 Feb 2020

DTCP licence

3 files
Licence Copy with Land Schedule25 Feb 2020Renewal of Licence No. 102 of 201125 Feb 2020Approval of Change of Developer25 Feb 2020

Environment clearance

1 file
Environment Clearance25 Feb 2020

Fire safety

4 files
Approval of Fire NOC, Phase II25 Feb 2020Fire NOC, Phase I25 Feb 2020Approval of Fire Scheme25 Feb 2020Approval of Fire NOC, Phase III25 Feb 2020

Other NOCs and clearances

8 files
Renewal of CTE25 Feb 2020NOC for Forest25 Feb 2020Renewal of AAI25 Feb 2020

Money

Accounts and finance

5 files
CA Certificate on the Application’s Figures11 Aug 2020Non-Default Certificate from a CA11 Aug 2020Financials for FY2018-196 Jul 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit14 Aug 2020

HARERA’s orders

HARERA’s orders

1 file
Extension of Mining Apporval25 Feb 2020

Other filings

Other filings

1 file
Single Line Diagram26 Feb 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

102 OF 2011 · Godrej Projects Development Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 6 Dec 2029

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 14 Aug 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

102 OF 2011: 28 parcels, 22.1234 acres in all, in Gurgaon (incompletely identified), tehsil Gurgaon.

The licence register prints the same licensed area, 22.12 acres.

  • rectangle 294, kila 294/214 biswa 9 biswansi
  • rectangle 11354, kila 11354/6370/303/214 biswa 17 biswansi
  • rectangle 299, kila 2991 bigha 16 biswa
  • rectangle 300, kila 3001 bigha 16 biswa
Show the other 24 parcels
  • rectangle 301, kila 3011 bigha 14 biswa
  • rectangle 11358, kila 11358/3061 bigha 16 biswa
  • rectangle 11348, kila 11348/2961 bigha
  • rectangle 302, kila 3021 bigha 8 biswa
  • rectangle 11352, kila 11352/298/2/11 biswa 6 biswansi
  • rectangle 11354, kila 11354/6370/303/12 biswa 15 biswansi
  • rectangle 11355, kila 11355/6371/303/16 biswa
  • rectangle 11356, kila 11356/6371/303/11 biswa 10 biswansi
  • rectangle 11345, kila 11345/2952 bigha
  • rectangle 11353, kila 11353/6370/30311 biswa
  • rectangle 11357, kila 11357/3061 bigha 17 biswa
  • rectangle 11351, kila 11351/2981 bigha 8 biswa
  • rectangle 293, kila 2933 bigha 2 biswa
  • rectangle 294, kila 294/12 bigha 13 biswa 11 biswansi
  • rectangle 11346, kila 11346/295/110 biswa
  • rectangle 11347, kila 11347/296/12 bigha 10 biswa
  • rectangle 11349, kila 11349/297/12 bigha 10 biswa
  • rectangle 11346, kila 11346/295/21 bigha 10 biswa
  • rectangle 11347, kila 11347/296/210 biswa
  • rectangle 11349, kila 11349/297/210 biswa
  • rectangle 11352, kila 11352/298/2/213 biswa 5 biswansi
  • rectangle 11355, kila 11355/6371/303/217 biswa
  • rectangle 11356, kila 11356/6371/303/21 bigha 15 biswa 6 biswansi
  • rectangle 11350, kila 11350/2971 bigha

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Gurgaon (incompletely identified), tehsil Gurgaon. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 294, kila 294/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, residential flat
₹7,700 per sq ft

Sector 104, collector rates effective 1 Apr 2026, Gurugram tehsil. 2 tehsil lists price this sector; this is the higher. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan25 Feb 2020

Layout plan

1 file
Latest Layout Plan26 Feb 2020

Building plans

2 files
Approved Building Plans, Full Set26 Feb 2020Approval of Building Plan25 Feb 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (41 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1314 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Godrej Projects Development

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.