Skip to content
Under construction

M3M Capital

by M3M India · Sector 113, Gurugram

Not on our price list yet

Possession 30 Jun 2026 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 113, Gurugram0.6 km from Dwarka Expressway, in a straight linePrices and what changed
Home types
2.5, 3.5 and 4.5 BHK
Carpet area
about 890 sq ft
In m²about 82.7 m², the average flat, as declared
Registered by
UNION BUILDMART PRIVATE LIMITEDthe company that filed it, for M3M India
Timeline
  1. 18 Jan 2022Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Jun 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026
  3. 29 Jun 2027Registration valid toHARERA, read 4 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside4.856 acres in all, by use
  • Parks and playgrounds2.248 acres · 46%
  • Roads1.262 acres · 26%
  • Other usesas the form names them: Open0.679 acres · 14%
  • Apartment buildings0.667 acres · 14%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Lifts3 lift per tower
  • FloorsVitrified tiles/laminated wooden floor/ceramic tile
  • WallsPlaster with OBD
  • WindowsGlass with aluminium framing sliding
  • Main doorHard wood door frame with flush door /laminate
  • Electrical fittingsAs per approved make
  • Gas pipelineService provider

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 113, GurugramSector 113, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.6 km
  • Delhi–Gurugram–SNB RRTS5.0 km
  • Sohna Elevated Corridor (NH-248A)9.3 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 13 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 4
  • Registered, no OC or CC yet: 9

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is M3M Capital registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/531/263/2022/06. Valid to 29 Jun 2027.

The source ↗
What is the possession timeline for M3M Capital?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Jun 2026. Its registration runs to 29 Jun 2027; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around M3M Capital?From the records · Map pin and road lines, read 6 Sep 2026

M3M Capital is in Sector 113, Gurugram; the site address declared to HARERA is Sector -113, Gurugram Manesar Urban Complex, Gurugram, Haryana.. In a straight line it is about 0.6 km from Dwarka Expressway, 5.0 km from Delhi–Gurugram–SNB RRTS and 9.3 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building M3M Capital?From the records · HARERA, read 4 Nov 2026

M3M Capital is a M3M India project, registered by its company UNION BUILDMART PRIVATE LIMITED.

The source ↗M3M India's projects and court record

The records

What the registers hold for M3M Capital: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/531/263/2022/06: Registered. Valid to 29 Jun 2027.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 106 OF 2021 is on the DTCP register: Licence ends soon; the register prints its validity to 15 Dec 2026.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 18 Jan 2022, building plans 18 Jan 2022.Declared to HARERA, read 29 Oct 2026
The court record of M3M India’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Licence 106 OF 2021 ends soon

    Named in this project’s application. Valid to 15 Dec 2026. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 37 HARERA files, with the dates we read them
Registration no.
GGM/531/263/2022/06
Registration valid till
29 Jun 2027
Declared possession
30 Jun 2026

Declared by the promoter to HARERA

Land area
4.856 (Acre) (19,651.53 sq m)
FAR
1.25 proposed
licence
106 of 2021 dated 16.12.2021
Estimated project cost
₹599.66 crore
Cost of land
₹122.74 crore
Layout plan, declared approved (field 5a)
18 Jan 2022
Building plans, declared approved
18 Jan 2022
Construction to start
18 Jan 2022
Completion declared for
30 Jun 2026
Declared inventory · 5 types

Declared inventory

  • Apartment/Shops/Other Buildings · 136 units · 11,147.61 sq m carpet · 1 tower · total for 136 flats, about 82 m² each
  • Apartment/Shops/Other Buildings · 136 units · 11,819.48 sq m carpet · 1 tower · total for 136 flats, about 86.9 m² each
  • Apartment/Shops/Other Buildings · 144 units · 11,718.03 sq m carpet · 1 tower · total for 144 flats, about 81.4 m² each
  • Apartment/Shops/Other Buildings · 144 units · 11,718.03 sq m carpet · 1 tower · total for 144 flats, about 81.4 m² each
  • Apartment/Shops/Other Buildings · 84 units · 6,830.42 sq m carpet · 1 tower · total for 84 flats, about 81.3 m² each
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. LICENCE — declared: already been obtained (16 Dec 2021)
  • II. BUILDING PLAN APPROVAL — declared: already been obtained (18 Jan 2022)
  • III. FOREST NOC — declared: already been obtained (7 Aug 2018)
  • IV. ARAVALI NOC — declared: already been obtained (27 Aug 2018)
On file with HARERA · 37 files

On file with HARERA (37)

Plans

Site plan

2 files
Site Plan & Area Summary20 Jan 2022Approved Site Plan18 Jan 2022

Layout plan

3 files
Resi T3A & B First Lvl & Typical Lvl Layout & Area Details20 Jan 2022Resi T3A, 3B, 3C Still Layout & Area Details20 Jan 2022Latest Layout Plan18 Jan 2022

Zoning plan

1 file
Zoning Plan18 Jan 2022

Demarcation plan

1 file
Demarcation Plan18 Jan 2022

Building plans

8 files
Resi T3C Section 1 & 220 Jan 2022Resi T1 Elevation 3 & 420 Jan 2022Resi T3A,3B Section 1 & 220 Jan 2022

Floor plans

3 files
Resi T1 2 to 4 Typical Lvl & Area20 Jan 2022Basement Plan20 Jan 2022Stilt Level Plan20 Jan 2022

Services

Sewerage and drainage

2 files
Drainage Layout Plan & Area Details2 Feb 2022Sewer Layout Plan2 Feb 2022

Water supply

2 files
Domestic Water Layout Plan2 Feb 2022Flushing Water Layout Plan2 Feb 2022

Roads

1 file
Road Layout Plan2 Feb 2022

Landscape and green areas

1 file
Landscape Plan15 Apr 2022

Approvals and clearances

Occupation certificate (OC)

1 file
Occupation Certificate26 Aug 2026

DTCP licence

1 file
Licence Copy with Land Schedule4 Mar 2022

Fire safety

2 files
Fire Fighting Site Plan & Area Summary15 Apr 2022Fire Fighting Layout Plan15 Apr 2022

Land records

Land records

2 files
Approved Site Plan with Kila Khasra for RERA15 Apr 2022Revenue Record Entry of Licence and Collaboration19 Jan 2022

Money

Accounts and finance

3 files
Cash Flow Statement8 Mar 2022CA Certificate on the Application’s Figures2 Feb 2022Non-Default Certificate from a CA2 Feb 2022

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit4 Mar 2022

Company papers

1 file
Board Resolution20 Jan 2022

HARERA’s orders

HARERA’s orders

2 files
Extension No. 10 of 2026 dated 23.04.202624 Apr 2026The Earlier registration certificate no. RC/REP/HARERA/GGM/531/263/2022/06 dated O2.O2.2O22 stands amended with the same registration certificate no. RC/REP/HARERA/GGM/531/263/2022/06 dated 28.O9.2022 after incorporating additional FAR7 Nov 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

106 OF 2021 · Union Buildmart Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 15 Dec 2026

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 20 Jan 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

106 OF 2021

DTCP’s page showed no land schedule for licence 106 OF 2021 when Bhumiq read it on 18 Oct 2026. verify at source

Collector rate, residential flat
₹7,700 per sq ft

Sector 113, collector rates effective 1 Apr 2026, Gurugram tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Site Plan & Area Summary20 Jan 2022Approved Site Plan18 Jan 2022

Layout plan

3 files
Resi T3A & B First Lvl & Typical Lvl Layout & Area Details20 Jan 2022Resi T3A, 3B, 3C Still Layout & Area Details20 Jan 2022Latest Layout Plan18 Jan 2022

Building plans

8 files
Resi T3C Section 1 & 220 Jan 2022Resi T1 Elevation 3 & 420 Jan 2022Resi T3A,3B Section 1 & 220 Jan 2022Resi T1 Elevation 1 & 220 Jan 2022Resi T1 Section 1 & 220 Jan 2022Resi T3A,3B Elevation 1 & 220 Jan 2022

Floor plans

3 files
Resi T1 2 to 4 Typical Lvl & Area20 Jan 2022Basement Plan20 Jan 2022Stilt Level Plan20 Jan 2022

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (37 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1847 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on M3M India

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.