Raheja Trinity

by Raheja Developers · Sector 84, Gurugram

Not on our price list yet

Possession 27 Aug 2022 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 84, Gurugram1.1 km from Dwarka Expressway, in a straight linePrices and what changed
Registered
25 Jul 2017
Registered by
RAHEJA DEVELOPERS LTD.the company that filed it, for Raheja Developers
Timeline
  1. 31 Oct 2013Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 25 Jul 2017Registered with HARERAHARERA, read 4 Nov 2026
  3. 25 Jul 2022Registration valid toHARERA, read 4 Nov 2026
  4. 27 Aug 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

In each home
  • LiftsModern high class lifts
  • FloorsGranite/marble/vitrified tiles in common areas
  • BathroomsVitrified/ceramic tile flooring/walls, high quality CP fitting and aceessories
  • Electrical fittingsInternational standards electrical wiring and outlets, separate metering for each SHOP. power backup.

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 84, GurugramSector 84, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20251.1 km
  • Delhi–Gurugram–SNB RRTS2.3 km
  • Sohna Elevated Corridor (NH-248A)7.5 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 15 projects in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 15

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is Raheja Trinity registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 24 OF 2017, registered on 25 Jul 2017. The register’s record shows an end date of 25 Jul 2022. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for Raheja Trinity?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 27 Aug 2022. Its registration runs to 25 Jul 2022; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Raheja Trinity?From the records · Map pin and road lines, read 6 Sep 2026

Raheja Trinity is in Sector 84, Gurugram; the site address declared to HARERA is Sector-84, Gurugram. In a straight line it is about 1.1 km from Dwarka Expressway, 2.3 km from Delhi–Gurugram–SNB RRTS and 7.5 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Raheja Trinity?From the records · HARERA, read 4 Nov 2026

Raheja Trinity is a Raheja Developers project, registered by its company RAHEJA DEVELOPERS LTD..

The source ↗Raheja Developers's projects and court record

The records

What the registers hold for Raheja Trinity: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 24 OF 2017: Registration lapsed. The register’s record shows an end date of 25 Jul 2022.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 26 OF 2013 is on the DTCP register: Licence lapsed; the register prints its validity to 16 May 2019.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 31 Oct 2013, building plans 31 Oct 2013.Declared to HARERA, read 29 Oct 2026
The court record of Raheja Developers’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 26 OF 2013 lapsed

    Named in this project’s application. Valid to 16 May 2019; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 25 Jul 2022. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 10 HARERA files, with the dates we read them
Registration no.
24 OF 2017
Registration date
25 Jul 2017
Registration valid till
25 Jul 2022
Declared possession
27 Aug 2022

Declared by the promoter to HARERA

Land area
2.281 (Acre) (9,230.88 sq m)
FAR
3.98 proposed of 3.99 permissible
licence
26 of 2013
Estimated project cost
₹241.00 crore
Cost of land
₹117.25 crore
Layout plan, declared approved (field 5a)
31 Oct 2013
Building plans, declared approved
31 Oct 2013
Completion declared for
27 Aug 2022
Declared inventory · 6 types

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 1 · 103 units
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 2 · 161 units
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 3 · 1 unit
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 4 · 1 unit
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 5 · 1 unit
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 6 · 1 unit
Statutory approvals, as declared · 6

Statutory approvals, as declared

  • I. LICENSE NO. 26 OF 2013 — declared: already been obtained (17 May 2013)
  • II. AAI PERMISSION — declared: already been obtained (30 May 2016)
  • III. CTE EXTENSION — declared: already been obtained (24 Jun 2017)
  • IV. ENVIRONMENT CLEARANCE — declared: already been obtained (17 Oct 2014)
  • V. FOREST NOC — declared: already been obtained (28 Feb 2014)
  • VI. WATER SUPPLY — declared: already been obtained (3 Oct 2013)
On file with HARERA · 10 files

On file with HARERA (10)

Plans

Site plan

1 file
Approved Site Plan18 Jan 2020

Layout plan

1 file
Latest Layout Plan18 Jan 2020

Zoning plan

1 file
Zoning Plan18 Jan 2020

Demarcation plan

1 file
Demarcation Plan18 Jan 2020

Building plans

1 file
Approved Building Plans, Full Set18 Jan 2020

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule18 Jan 2020

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration18 Jan 2020

Money

Accounts and finance

2 files
CA Certificate on the Application’s Figures18 Jan 2020Non-Default Certificate from a CA18 Jan 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit18 Jan 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

26 OF 2013 · Raheja Developers Ltd. · GURGAON-MANESAR

Licence valid to 16 May 2019

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 10 Feb 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

26 OF 2013: 5 parcels, 2.2813 acres in all, in Sihi (hadbast 108), tehsil Manesar.

The licence register prints the same licensed area, 2.28 acres.

  • 36//21/17 kanal 14 marla
  • 36//22/13 kanal 11 marla
  • 42//5/2/12 kanal 14 marla
  • 43//1/11 kanal 2 marla
Show the other 1 parcel
  • 37//25/23 kanal 4 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Sihi (hadbast 108), tehsil Manesar. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 36//21/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, commercial property
₹2,21,800 per sq yd

Sector 84, collector rates effective 1 Apr 2026, Manesar tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a property is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan18 Jan 2020

Layout plan

1 file
Latest Layout Plan18 Jan 2020

Building plans

1 file
Approved Building Plans, Full Set18 Jan 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (10 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/987 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Raheja Developers

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.