Skip to content

AIRIA

by Reach Promoters · Sector 68, Gurugram

Not on our price list yet

Possession 31 Dec 2032 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 68, Gurugram0.3 km from Sohna Elevated Corridor (NH-248A), in a straight line
Registered by
REACH PROMOTERS PRIVATE LIMITEDthe company that filed it, for Reach Promoters
Timeline
  1. 5 Jun 2025Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2032Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside36,169 m² in all, by use
  • Apartment buildings18,628 m² · 52%
  • Roads11,308 m² · 31%
  • Green belts6,233 m² · 17%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningProvision/ TAP OFF for AIR conditioning in the units. low side HVAC/ ducting WORK/ AHU installation/ piping WORK to be DONE by unit owner/ allottee.
  • LiftsStandard electrical elevators
  • FloorsTile/ stone (common areas)
  • WallsTile/ stone/paint (common areas)
  • BathroomsCommon toilets (standard make)
  • WindowsAs per approved layout/ elevation
  • Electrical fittingsStandard make electrical fittings in common areas
  • Wi-Fi and broadbandProvision based on available operators.

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 68, GurugramSector 68, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Sohna Elevated Corridor (NH-248A)0.3 km
  • Dwarka ExpresswayOpen, 17 Aug 20255.7 km
  • Delhi–Gurugram–SNB RRTS5.7 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 2

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is AIRIA registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as GGM/974/706/2025/77. Valid to 31 Dec 2032.

The source ↗
What is the possession timeline for AIRIA?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2032. Its registration runs to 31 Dec 2032; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around AIRIA?From the records · Map pin and road lines, read 6 Sep 2026

AIRIA is in Sector 68, Gurugram; the site address declared to HARERA is Sector 68. In a straight line it is about 0.3 km from Sohna Elevated Corridor (NH-248A), 5.7 km from Dwarka Expressway and 5.7 km from Delhi–Gurugram–SNB RRTS.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building AIRIA?From the records · HARERA, read 3 Nov 2026

AIRIA is a Reach Promoters project, registered by its company REACH PROMOTERS PRIVATE LIMITED.

The source ↗Reach Promoters's projects and court record

The records

What the registers hold for AIRIA: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/974/706/2025/77: Registered. Valid to 31 Dec 2032.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 17 OF 2010 is on the DTCP register, valid to 12 Feb 2030.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 5 Jun 2025.Declared to HARERA, read 29 Oct 2026
The court record of Reach Promoters’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 91 HARERA files, with the dates we read them
Registration no.
GGM/974/706/2025/77
Registration valid till
31 Dec 2032
Declared possession
31 Dec 2032

Declared by the promoter to HARERA

Land area
8.9375 (Acre) (36,168.78 sq m)
FAR
2.4 proposed of 2.69 permissible
licence
17 of 2010 dated 13.02.2010 and 150 of 2022 dated 28.09.2022
Estimated project cost
₹1193.71 crore
Cost of land
₹65.63 crore
Building plans, declared approved
5 Jun 2025
Construction to start
1 Apr 2012
Completion declared for
31 Dec 2032
Declared inventory · 21 types

Declared inventory — 21 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 15 units · 868.725 sq m carpet · 1 tower
  • Apartment/Shops/Other Buildings · 15 units · 906.78 sq m carpet · 1 tower
  • Apartment/Shops/Other Buildings · 15 units · 953.28 sq m carpet · 1 tower
  • Apartment/Shops/Other Buildings · 15 units · 981.57 sq m carpet · 1 tower
  • Apartment/Shops/Other Buildings · 15 units · 1,002.06 sq m carpet · 1 tower
  • Apartment/Shops/Other Buildings · 15 units · 1,069.995 sq m carpet · 1 tower
  • Apartment/Shops/Other Buildings · 5 units · 484.885 sq m carpet · 1 tower
  • Apartment/Shops/Other Buildings · 15 units · 1,730.895 sq m carpet · 1 tower
Statutory approvals, as declared · 19

Statutory approvals, as declared

  • I. LICENSE- 17 OF 2010 — declared: already been obtained (13 Feb 2010)
  • II. ASSURANCE OF SEWERAGE CONNECTION — declared: already been obtained (7 Apr 2025)
  • III. ASSURANCE OF STORM WATER — declared: already been obtained (8 Apr 2025)
  • IV. ASSURANCE OF WATER SUPPLY FOR CONSTRUCTION PURPOSE — declared: already been obtained (7 Apr 2025)
  • V. ASSURANCE FOR WATER SUPPLY OF DRINKINGWATER — declared: already been obtained (9 Apr 2025)
  • VI. EC — declared: already been obtained (31 Aug 2024)
  • VII. FOREST NOC — declared: already been obtained (18 Jan 2020)
  • VIII. AAI — declared: already been obtained (24 Apr 2024)
  • IX. ELECTRICAL LOAD ASSURANCE — declared: already been obtained (25 Nov 2022)
  • X. BUILDING PLAN — declared: already been obtained (5 Jun 2025)
  • XI. SERVICE ESTIMATES AND PLAN — declared: already been obtained (1 Jul 2025)
  • XII. FIRE SCHEME APPROVAL — declared: already been obtained (25 Jun 2025)
  • XIII. LICENSE 150 OF 2022 — declared: already been obtained (28 Sept 2022)
  • XIV. EC 17 OF 2010 — declared: already been obtained (8 Aug 2011)
  • XV. AAI 17 OF 2010 — declared: already been obtained (14 Dec 2011)
  • XVI. BUILDING PLAN 17 OF 2010 — declared: already been obtained (16 Jan 2015)
  • XVII. SERVICE PLAN & ESTIMATES 17 OF 2010 — declared: already been obtained (18 Sept 2015)
  • XVIII. FIRE SCHEME APPRROVEL 17 OF 2010 — declared: already been obtained (14 Mar 2015)
  • XIX. FOREST NOC 17 OF 2010 — declared: already been obtained (3 Oct 2012)
On file with HARERA · 91 files

On file with HARERA (91)

Plans

Site plan

4 files
Site Plan 17 of 20104 Aug 2025Site Plan (Service)7 Jun 2025Site Plan (Architecture)7 Jun 2025Approved Site Plan5 Jun 2025

Layout plan

1 file
Latest Layout Plan5 Jun 2025

Zoning plan

1 file
Zoning Plan5 Jun 2025

Demarcation plan

2 files
Superimposed Demarcation4 Aug 2025Demarcation Plan5 Jun 2025

Building plans

8 files
BR-III 17 of 20104 Aug 2025Section Ar - 27 Jun 2025North Side Elevation Plan7 Jun 2025

Floor plans

18 files
4th Floor Plan (Area Calculation Plan)7 Jun 20252nd Floor Plan (Area Calculation Plan)7 Jun 20251st Floor Plan (Area Calculation Plan)7 Jun 2025

Services

Sewerage and drainage

4 files
Storm Water Drainage Plan4 Aug 2025Sewerage Scheme Plan4 Aug 2025Assurance of Sewerage Connection16 May 2025Assurance for Storm Water16 May 2025

Water supply

2 files
Water Supply Plan4 Aug 2025Assurance for Water Supply16 May 2025

Electricity

1 file
Electrical Load7 Jun 2025

Roads

1 file
Roads Plan4 Aug 2025

Service plans

5 files
Service Estimate 150 of 20224 Aug 2025Service Plan Estimate 17 of 20104 Aug 2025Service Estimate Booklet 150 of 20224 Aug 2025

Approvals and clearances

Occupation certificate (OC)

1 file
OC Merged4 Aug 2025

DTCP licence

6 files
LC-IV 17 of 20104 Aug 2025LOI 17 of 20104 Aug 2025License 17 of 20104 Aug 2025

Environment clearance

2 files
EC 17 of 20104 Aug 2025Enviornment Clearence16 May 2025

Fire safety

4 files
Fire Fighting Scheme 17 of 20104 Aug 2025Approval of Fire Fighting Scheme4 Aug 2025Sire Plan (Fire)7 Jun 2025Fire Scheme7 Jun 2025

Other NOCs and clearances

4 files
NOC for Forest Clarification 17 of 20104 Aug 2025Tree Cutting NOC7 Jun 2025AAI16 May 2025Forest NOC16 May 2025

Land records

Land records

7 files
Sale Deed 17 of 20104 Aug 2025Non Encumbrance Certificate4 Aug 2025Aks-Sizra4 Aug 2025

Sales papers

Allotment and sale agreements

3 files
Conveyance Deed Airia20 Aug 2025Allotment Letter Airia20 Aug 2025Agreement for Sale Airia20 Aug 2025

Money

Accounts and finance

13 files
Approval for Change in Bank Account24 Feb 2026Receipt20 Aug 2025Cash Flow Statement28 Jul 2025

The promoter’s papers

Declarations and affidavits

3 files
Application Form Airia20 Aug 2025Bank Undertaking28 Jul 2025The Promoter’s Declaration on Affidavit28 Jul 2025

Other filings

Other filings

1 file
HUDA Construction16 May 2025

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

17 OF 2010 · Reach Promotors Pvt. Ltd · GURGAON-MANESAR

Licence valid to 12 Feb 2030

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

150 OF 2022 · Reach Promoters Pvt. Ltd · GURGAON-MANESAR

Licence valid to 27 Sept 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 9 Jun 2025 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 3 Nov 2026

Land under the 2 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

17 OF 2010: 16 parcels, 6.2625 acres in all, in Badshapur (hadbast 87), tehsil Badshahpur.

The licence register prints the same licensed area, 6.26 acres.

  • 132//18 kanal
  • 132//10/13 kanal 9 marla
  • 132//10/23 kanal 9 marla
  • 132//118 kanal
Show the other 12 parcels
  • 132//128 kanal
  • 132//133 kanal 2 marla
  • 132//2/1 min7 marla
  • 132//2/2 min2 kanal
  • 132//21/2 min13 marla
  • 132//22 min1 kanal 3 marla
  • 132//262 marla
  • 132//271 kanal
  • 132//8 min15 marla
  • 132//9 min7 kanal 9 marla
  • rectangle 132, kila 21/32 kanal
  • rectangle 132, kila 21/413 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

150 OF 2022: 12 parcels, 6.95 acres in all, in Badshapur (hadbast 87), tehsil Badshahpur.

The licence register prints the same licensed area, 6.95 acres.

  • 122//17/25 kanal 11 marla
  • 122//247 kanal 15 marla
  • 122//25/11 kanal
  • 122//25/27 kanal
Show the other 8 parcels
  • 133//14/21 kanal 8 marla
  • 133//15/12 kanal 16 marla
  • 133//15/23 kanal 16 marla
  • 133//15/31 kanal 8 marla
  • 133//45 kanal 10 marla
  • 133//58 kanal
  • 133//68 kanal
  • 133//7/13 kanal 8 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Badshapur (hadbast 87), tehsil Badshahpur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 132//1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

4 files
Site Plan 17 of 20104 Aug 2025Site Plan (Service)7 Jun 2025Site Plan (Architecture)7 Jun 2025Approved Site Plan5 Jun 2025

Layout plan

1 file
Latest Layout Plan5 Jun 2025

Building plans

8 files
BR-III 17 of 20104 Aug 2025Section Ar - 27 Jun 2025North Side Elevation Plan7 Jun 2025BR III7 Jun 2025Terrace Plan7 Jun 2025West Side Elevation Plan7 Jun 2025

Floor plans

18 files
4th Floor Plan (Area Calculation Plan)7 Jun 20252nd Floor Plan (Area Calculation Plan)7 Jun 20251st Floor Plan (Area Calculation Plan)7 Jun 2025Basement 4 (Area Calculation Plan)7 Jun 2025Ground Floor and Ground Coverage (Area Calculation Plan)7 Jun 2025Ground Floor7 Jun 2025

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (91 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3499 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Reach Promoters

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.