About this project

Key facts

Location
Sector 62, Gurugram3.8 km from Sohna Elevated Corridor (NH-248A), in a straight linePrices and what changed
Asking rate
₹20,000 a sq ft of carpet
Bhumiq team price list, 16 Sep 2026
Registered by
CONSCIENT INFRASTRUCTURE PRIVATE LIMITEDthe company that filed it, for Conscient Infrastructure
Timeline
  1. 31 Oct 2023Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 1 Oct 2030Possession, as declareddeclared to HARERA, read 29 Oct 2026
  3. 30 Oct 2030Registration valid toHARERA, read 4 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside4.844 acres in all, by use
  • Other uses1.298 acres · 27%
  • Roads1.025 acres · 21%
  • Parks and playgrounds0.969 acres · 20%
  • Pavements0.762 acres · 16%
  • Apartment buildings0.437 acres · 9%
  • Club house0.353 acres · 7%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningVRV system
  • KitchenFloor tiles & paint
  • Kitchen appliancesModular kitchen
  • LiftsPassenger/service/fireman lift
  • FloorsMarble/ premium quality tiles/ equivalent
  • WallsPaint surface
  • BathroomsStandard CP fitting + WC+washbasin
  • WindowsAluminium/ UPVC/ equivalent

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 62, GurugramSector 62, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Sohna Elevated Corridor (NH-248A)3.8 km
  • Delhi–Gurugram–SNB RRTS6.3 km
  • Dwarka ExpresswayOpen, 17 Aug 20258.9 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 6 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 3
  • Registered, no OC or CC yet: 3

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is Conscient Elevate Reserve registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/757/489/2023/101. Valid to 30 Oct 2030.

The source ↗
What is the possession timeline for Conscient Elevate Reserve?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 1 Oct 2030. Its registration runs to 30 Oct 2030; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Conscient Elevate Reserve?From the records · Map pin and road lines, read 6 Sep 2026

Conscient Elevate Reserve is in Sector 62, Gurugram; the site address declared to HARERA is Sector-62, Village Ullhawas, Wazirabad, Gurugram, Haryana. In a straight line it is about 3.8 km from Sohna Elevated Corridor (NH-248A), 6.3 km from Delhi–Gurugram–SNB RRTS and 8.9 km from Dwarka Expressway.

The source ↗
What does a home in Conscient Elevate Reserve cost, and how does that compare nearby?From the records · Bhumiq team price list, 16 Sep 2026

The Bhumiq team's price list has ₹20,000 a sq ft of carpet area (16 Sep 2026). Prices change; ask the developer for its current price list.

What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty

The records

What the registers hold for Conscient Elevate Reserve: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/757/489/2023/101: Registered. Valid to 30 Oct 2030.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: layout plan 31 Oct 2023, building plans 31 Oct 2023.Declared to HARERA, read 29 Oct 2026
The court record of Conscient Infrastructure’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 97 HARERA files, with the dates we read them
Registration no.
GGM/757/489/2023/101
Registration valid till
30 Oct 2030
Declared possession
1 Oct 2030
Asking price (indicative)
₹20,000 / sq ft of carpet area

Bhumiq team price list · as of 16 Sept 2026 · a quoted rate, not a registry figure

Declared by the promoter to HARERA

Land area
4.84375 (Acre) (19,601.96 sq m)
FAR
3.23 proposed of 3.23 permissible
licence
Licence No. 114/2023 dated 02.06.2023 granted by Town and Country Planning Department, Haryana Government
Estimated project cost
₹1083.59 crore
Cost of land
₹301.49 crore
Layout plan, declared approved (field 5a)
31 Oct 2023
Building plans, declared approved
31 Oct 2023
Construction to start
29 Feb 2024
Completion declared for
1 Oct 2030
Declared inventory · 4 types

Declared inventory

  • Apartment/Shops/Other Buildings · 240 units · 35,866.644 sq m carpet · 2 towers
  • Apartment/Shops/Other Buildings · 190 units · 7,605.395 sq m carpet · 2 towers
  • Apartment/Shops/Other Buildings · 1 unit · 1,426.61 sq m carpet · 2 towers
  • Apartment/Shops/Other Buildings · 43 units · 1,001.6 sq m carpet · 1 tower
Statutory approvals, as declared · 7

Statutory approvals, as declared

  • I. ELECTRICITY LOAD AVAILABILITY — declared: already been obtained (9 Jun 2023)
  • II. STORM WATER DRAINAGE — declared: already been obtained (16 Jun 2023)
  • III. ZONING PLAN APPROVAL — declared: already been obtained (2 Jun 2023)
  • IV. FOREST NOC — declared: already been obtained (28 Apr 2023)
  • V. TREE CUTTING PERMISSION — declared: already been obtained (10 Jul 2023)
  • VI. WATER SUPPLY — declared: already been obtained (22 Jun 2023)
  • VII. SEWAGE DISPOSAL — declared: already been obtained (15 Jun 2023)
On file with HARERA · 97 files

On file with HARERA (97)

Plans

Site plan

1 file
Approved Site Plan16 Feb 2024

Layout plan

1 file
Latest Layout Plan16 Feb 2024

Zoning plan

1 file
Zoning Plan21 Oct 2023

Demarcation plan

1 file
Demarcation Plan21 Oct 2023

Building plans

26 files
9th & 41st Floor, Roof Plan Mumty Area Calculation (Tower-B)-116 Feb 2024Section-Aa & B-B All Elevation ( EWS)16 Feb 2024Left Elevation( Tower-A)16 Feb 2024

Floor plans

31 files
Composite Type Floor Plan16 Feb 2024Ground Floor Plan16 Feb 2024Basement-01 Area Calculation16 Feb 2024

Services

Sewerage and drainage

2 files
Assurance for Storm Water16 Feb 2024Assurance for Sewerage16 Feb 2024

Water supply

8 files
Domestic Water Supply Schematic (Tower-A)16 Feb 2024Assurance Water16 Feb 2024Flushing Water Supply Schematic (Tower-A)16 Feb 2024

Electricity

1 file
Assurance of Power16 Feb 2024

Landscape and green areas

1 file
Green Area Calculation16 Feb 2024

Service plans

3 files
3rd Floor Service Floor Plan, Typical Floor Plan16 Feb 2024Basement-01 ( Services Plan)16 Feb 2024Service Plans on the Layout16 Feb 2024

Approvals and clearances

Completion certificate (CC)

1 file
Section-Aa, Bb & CC (Club)16 Feb 2024

DTCP licence

4 files
LC-IV (Bilateral Agreement)16 Feb 2024LOI16 Feb 2024LC-IV-A (Bilateral Agreement)16 Feb 2024Licence Copy with Land Schedule21 Oct 2023

Environment clearance

1 file
Environment Clearance16 Feb 2024

Fire safety

1 file
Site Plan( Irrigation Line, External Fire Line, Water Supply, Sewerage & Storm Line)16 Feb 2024

Other NOCs and clearances

3 files
Airport Height Clearance16 Feb 2024Tree Cutting Permission16 Feb 2024Forest Clearance16 Feb 2024

Land records

Land records

3 files
Collaboration Agreement( Neeru Jain +Cipl)16 Feb 2024Collaboration Agreement( Land Owner to Cipl)16 Feb 2024Revenue Record Entry of Licence and Collaboration21 Oct 2023

Money

Accounts and finance

4 files
CA Certificate on the Application’s Figures16 Feb 2024Non-Default Certificate from a CA16 Feb 2024Cash Flow Statement16 Feb 2024Certificate of Cost Incurred Elevate Reserve16 Feb 2024

The promoter’s papers

Declarations and affidavits

3 files
The Promoter’s Declaration on Affidavit16 Feb 2024Undertaking for Mining16 Feb 2024Bank Undertaking16 Feb 2024

Other filings

Other filings

1 file
N.E.C Certificate DTD.27.10.202316 Feb 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared Licence No. 114/2023 dated 02.06.2023 granted by Town and Country Planning Department, Haryana Government. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Gurugram bench · submitted 21 Oct 2023 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Collector rate, residential flat
₹9,900 per sq ft

Sector 62, collector rates effective 1 Apr 2026, Wazirabad tehsil. 2 tehsil lists price this sector; this is the higher. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan16 Feb 2024

Layout plan

1 file
Latest Layout Plan16 Feb 2024

Building plans

26 files
9th & 41st Floor, Roof Plan Mumty Area Calculation (Tower-B)-116 Feb 2024Section-Aa & B-B All Elevation ( EWS)16 Feb 2024Left Elevation( Tower-A)16 Feb 2024West and South Elevation & Section 2-2 ( Retail)16 Feb 2024BR-III16 Feb 2024Roof Plan( Retail)16 Feb 2024

Floor plans

31 files
Composite Type Floor Plan16 Feb 2024Ground Floor Plan16 Feb 2024Basement-01 Area Calculation16 Feb 2024Toilet Detail-Tower-A & B,club,ews16 Feb 2024Typical Floor Plan( Tower-B)16 Feb 2024Composite Refuge Floor Plan16 Feb 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (97 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2618 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Conscient Infrastructure

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

₹20,000/sq ftBook a site visitAsk

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.