Possession 30 Apr 2023 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 86, Gurugram2.7 km from Delhi–Gurugram–SNB RRTS, in a straight linePrices and what changed
Carpet area
572–592 sq ft
In m²about 53–55 m², as declared
Registered
16 Jan 2019
Registered by
PYRAMID INFRATECH PVT. LTD.the company that filed it, for Pyramid Infratech
Timeline
  1. 16 Jan 2019Registered with HARERAHARERA, read 4 Nov 2026
  2. 30 Apr 2023Possession, as declareddeclared to HARERA, read 29 Oct 2026
  3. 30 Jul 2024Registration valid toHARERA, read 4 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

810homes, 572 to 592 sq ft of carpet area
  • Under 1,000 sq ft572–592 sq ft810

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

In each home
  • KitchenWall- OBD/color WASH, 2 FT tile on kitchen counter, ADN tile/ stone on kitchen counter
  • Lifts2 lifts as per sanctioned PLAN.
  • FloorsTiles/IPS
  • WallsOBD/color WASH
  • BathroomsCP/ PVC fittings
  • WindowsGlazed window 4 MM glass
  • Main doorFlush door
  • Electrical fittingsISI MARK

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 86, GurugramSector 86, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Delhi–Gurugram–SNB RRTS2.7 km
  • Dwarka ExpresswayOpen, 17 Aug 20253.2 km
  • Sohna Elevated Corridor (NH-248A)9.9 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 10 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 9
  • Other register states: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is PYRAMID ELITE registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/309/41/2019/03, registered on 16 Jan 2019. Ended 30 Jul 2024. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for PYRAMID ELITE?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Apr 2023. Its registration runs to 30 Jul 2024; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around PYRAMID ELITE?From the records · Map pin and road lines, read 6 Sep 2026

PYRAMID ELITE is in Sector 86, Gurugram; the site address declared to HARERA is Sector- 86, Manesar, Gurugram. In a straight line it is about 2.7 km from Delhi–Gurugram–SNB RRTS, 3.2 km from Dwarka Expressway and 9.9 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building PYRAMID ELITE?From the records · HARERA, read 4 Nov 2026

PYRAMID ELITE is a Pyramid Infratech project, registered by its company PYRAMID INFRATECH PVT. LTD..

The source ↗Pyramid Infratech's projects and court record

The records

What the registers hold for PYRAMID ELITE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/309/41/2019/03: Registration expired. Ended 30 Jul 2024.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 77 OF 2018 is on the DTCP register, valid to 16 May 2027.DTCP, read 3 Nov 2026
The court record of Pyramid Infratech’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 30 Jul 2024. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 7 HARERA files, with the dates we read them
Registration no.
GGM/309/41/2019/03
Registration date
16 Jan 2019
Registration valid till
30 Jul 2024
Declared possession
30 Apr 2023

Declared by the promoter to HARERA

Land area
5.6125 (Acre) (22,712.98 sq m)
FAR
the application prints 224, which is not a ratio
licence
77 OF 2018 dated 17/11/2018
Estimated project cost
₹128.98 crore
Cost of land
₹31.00 crore
Construction to start
15 May 2019
Completion declared for
30 Apr 2023
Declared inventory · 4 types

Declared inventory

  • Apartment/Shops/Other Buildings · 398 units · 54.014 sq m carpet · 7 towers · one flat
  • Apartment/Shops/Other Buildings · 206 units · 53.284 sq m carpet · 7 towers · one flat
  • Apartment/Shops/Other Buildings · 103 units · 53.165 sq m carpet · 7 towers · one flat
  • Apartment/Shops/Other Buildings · 103 units · 54.978 sq m carpet · 7 towers · one flat
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. APPROVED DRAWINGS FROM DTCP, HARYANA — declared: already been obtained (31 Dec 2018)
On file with HARERA · 7 files

On file with HARERA (7)

Plans

Site plan

1 file
Approved Site Plan2 Jan 2019

Layout plan

1 file
Latest Layout Plan2 Jan 2019

Building plans

1 file
Approved Building Plans, Full Set2 Jan 2019

Approvals and clearances

Occupation certificate (OC)

1 file
Occupation Certificate13 Aug 2024

DTCP licence

1 file
Licence Copy with Land Schedule2 Jan 2019

Money

Accounts and finance

1 file
Non-Default Certificate from a CA2 Jan 2019

HARERA’s orders

HARERA’s orders

1 file
EXTENSION NO. 11 of 2023 DATED 08.05.202315 Jun 2023

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

77 OF 2018 · Pyramid Infratech Pvt Ltd · GURGAON-MANESAR

Licence valid to 16 May 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 2 Jan 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

77 OF 2018: 14 parcels, 5.6125 acres in all, in Nawada fatehpur (hadbast 112), tehsil Manesar.

The licence register prints the same licensed area, 5.6125 acres.

  • 15//12/2/119 marla
  • 15//13/110 marla
  • 15//14/1min3 kanal 10 marla
  • 15//15/13 kanal 2 marla
Show the other 10 parcels
  • 15//15/2/18 marla
  • 15//3/22 kanal 18 marla
  • 15//48 kanal
  • 15//5/15 kanal
  • 15//6/13 kanal 18 marla
  • 15//6/24 kanal 2 marla
  • 15//7/13 kanal 18 marla
  • 15//7/24 kanal 2 marla
  • 15//8/1/1min2 kanal 8 marla
  • 15//8/1/22 kanal 3 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Nawada fatehpur (hadbast 112), tehsil Manesar. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 15//12/2/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No collector rate for a residential flat in Sector 86 in the lists Bhumiq reads, as of 28 Aug 2026. That is not confirmation that none exists.

Lenders that list this project

  • PNB Housing Finance’s approved-projects list carries “Pyramid Elite”, by M/s Pyramid Infratech Pvt. Ltd., code Gurgaon-0819-001063, approved 2019.

    PNB Housing Finance’s own page · read 26 Oct 2026 · www.pnbhousing.com ↗

A lender’s list prints no HARERA registration or licence number, so the Bhumiq team matched it to this project by its name and builder. A listing is the lender’s record of a project it has approved for home loans, not a loan offer.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan2 Jan 2019

Layout plan

1 file
Latest Layout Plan2 Jan 2019

Building plans

1 file
Approved Building Plans, Full Set2 Jan 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (7 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/356 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Pyramid Infratech

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.