Key facts

Location
Sector 53, Gurugram4.9 km from Delhi–Gurugram–SNB RRTS, in a straight line
Carpet area
about 2,434 sq ft
In m²about 226.1 m², the average flat, as declared
Registered
17 Oct 2017
Registered by
MONIKA INFRASTRUCTURE PRIVATE LIMITEDthe company that filed it, for Monika Infrastructure
Timeline
  1. 16 Aug 2016Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 17 Oct 2017Registered with HARERAHARERA, read 4 Nov 2026
  3. 30 Jun 2023Registration valid toHARERA, read 4 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside12,917 m² in all, by use
  • Apartment buildings5,164 m² · 40%
  • Roads2,718 m² · 21%
  • Parks and playgrounds2,312 m² · 18%
  • Pavements1,030 m² · 8%
  • Green belts943 m² · 7%
  • Parking750 m² · 6%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningVRV system in tower B. tower a YET to be planned.
  • KitchenKOTA in flooring and sink
  • Lifts3 lifts in tower B operational. make mitsubishi, speed 1.5 M/SEC.
  • FloorsGF central plaza - pavers/ tiles, common toilets - vitrified / ceramic tiles, corridors / passage - vitrified / ceramic tiles, retail shops - BARE shell, common staircase - KOTA stone.
  • WallsPlastered walls in SHOP
  • BathroomsSingle lever C.P. fittings, EWC, health faucet, WASH basin.
  • WindowsUPVC/aluminium sliding swing glass shutter
  • Electrical fittingsBranded modular switches and sockets.

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 53, GurugramSector 53, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Delhi–Gurugram–SNB RRTS4.9 km
  • Sohna Elevated Corridor (NH-248A)6.0 km
  • Dwarka ExpresswayOpen, 17 Aug 202510.5 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is Tapasya One registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 317 OF 2017, registered on 17 Oct 2017. Ended 30 Jun 2023. The register shows it as: Registration expired.

The source ↗
How is the connectivity around Tapasya One?From the records · Map pin and road lines, read 6 Sep 2026

Tapasya One is in Sector 53, Gurugram; the site address declared to HARERA is Sector 53 Wazirabad Gurugram. In a straight line it is about 4.9 km from Delhi–Gurugram–SNB RRTS, 6.0 km from Sohna Elevated Corridor (NH-248A) and 10.5 km from Dwarka Expressway.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Tapasya One?From the records · HARERA, read 4 Nov 2026

Tapasya One is a Monika Infrastructure project, registered by its company MONIKA INFRASTRUCTURE PRIVATE LIMITED.

The source ↗Monika Infrastructure's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for Tapasya One: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 317 OF 2017: Registration expired. Ended 30 Jun 2023.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 5 OF 2001 is on the DTCP register: Licence lapsed; the register prints its validity to 30 Aug 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 16 Aug 2016, building plans 16 Aug 2016.Declared to HARERA, read 29 Oct 2026
The court record of Monika Infrastructure’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 30 Jun 2023. HARERA Gurugram, read 4 Nov 2026. Source

  • Red flag: Licence 5 OF 2001 lapsed

    Named in this project’s application. Valid to 30 Aug 2024; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Red flag: Licence 115 OF 2004 lapsed

    Named in this project’s application. Valid to 26 Jul 2024; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 56 HARERA files, with the dates we read them
Registration no.
317 OF 2017
Registration date
17 Oct 2017
Registration valid till
30 Jun 2023

Declared by the promoter to HARERA

Land area
3.1918 (Acre) (12,916.76 sq m)
FAR
1.75 proposed of 1.75 permissible
licence
5 OF 2001(31.08.2001) AND 115 OF 2004(27.07.2004)
Estimated project cost
₹177.00 crore
Cost of land
₹1.06 crore
Layout plan, declared approved (field 5a)
16 Aug 2016
Building plans, declared approved
16 Aug 2016
Declared inventory · 2 types

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER A · 76 units · 13,351 sq m carpet · total for 76 flats, about 175.7 m² each
  • APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B · 6 units · 5,189 sq m carpet · total for 6 flats, about 864.8 m² each
Statutory approvals, as declared · 10

Statutory approvals, as declared

  • I. APPROVED ZOING PLAN — declared: already been obtained (26 Apr 2006)
  • II. ENVIRONMENT CLEARANCE — declared: already been obtained (20 Aug 2018)
  • III. CERTIFICATE OF REGISTRATION ISSUED BY THE LABOUR COMMISSIONER HARYANA & REGISTERING OFFICER, LABOUR DEPARTMENT HARYANA — declared: already been obtained (1 Jan 2016)
  • IV. BOCW REGISTRATION ISSUED BY THE ASSISTANT DIRECTOR (IS& H) GURUGRAM -II, REGISTRATION OFFICER CUM ASSESSING AUTHORITY , GOVERNMENT OF HARYANA — declared: already been obtained (18 Jan 2018)
  • V. NOC FROM POLLUTION BOARD — declared: already been obtained (29 Aug 2017)
  • VI. NOC FROM FOREST DEPT. — declared: already been obtained (28 Oct 2015)
  • VII. ARAVALI NOTIFICATION — declared: already been obtained (24 Nov 2015)
  • VIII. ASSURANCE LETTER FOR ELECTRICITY DEPARTMENT — declared: already been obtained (13 Feb 2017)
  • IX. NOC FROM HUDA FOR CONSTRUCTION — declared: already been obtained (6 Oct 2010)
  • X. NOC FROM AIRPORTS AUTHORITY — declared: already been obtained (30 Jan 2019)
On file with HARERA · 56 files

On file with HARERA (56)

Plans

Site plan

2 files
Site Plan28 Nov 2019Approved Site Plan22 Nov 2019

Layout plan

1 file
Latest Layout Plan22 Nov 2019

Zoning plan

1 file
Zoning Plan22 Nov 2019

Demarcation plan

2 files
Demarcation Plan and Letter7 Feb 2020Demarcation Plan22 Nov 2019

Building plans

5 files
BR-III7 Feb 2020BR-III Approval of Revised Building Plan22 Nov 2019Approved Building Plans, Full Set22 Nov 2019

Services

Sewerage and drainage

2 files
Sewerage Scheme22 Nov 2019Storm Water Drainage Scheme22 Nov 2019

Water supply

2 files
Water Assurance Letter22 Nov 2019Water Supply Scheme22 Nov 2019

Electricity

1 file
Electrical Load Sanction 1500KW22 Nov 2019

Roads

1 file
Roads Plans22 Nov 2019

Service plans

2 files
Service Estimate7 Feb 2020Service Plan Approval Letter7 Feb 2020

Approvals and clearances

Occupation certificate (OC)

3 files
Occupation Certificate6 Aug 2024OC Building Plan22 Nov 2019Approval Letter OC22 Nov 2019

DTCP licence

3 files
LOI7 Feb 2020LC-IV7 Feb 2020Licence Copy with Land Schedule22 Nov 2019

Environment clearance

2 files
Environment Clearance7 Feb 2020Environment Clearance22 Nov 2019

Fire safety

2 files
Fire Scheme Approval7 Feb 2020Fire Fighting Scheme22 Nov 2019

Other NOCs and clearances

7 files
Forest NOC7 Feb 2020Aravali Notification7 Feb 2020NOC from Airport Authority22 Nov 2019

Land records

Land records

2 files
Non Encumbrance Certificate7 Feb 2020Revenue Record Entry of Licence and Collaboration22 Nov 2019

Sales papers

Allotment and sale agreements

2 files
Draft Allotment Letter22 Nov 2019Draft Agreement22 Nov 2019

Money

Accounts and finance

7 files
Cash Flow Statement28 Nov 2019Non-Default Certificate from a CA22 Nov 2019Balance Sheet Fy 2016-1722 Nov 2019

The promoter’s papers

Declarations and affidavits

2 files
Rep-II7 Feb 2020The Promoter’s Declaration on Affidavit22 Nov 2019

Company papers

1 file
Bocw Registration Issued by the Assistant Director (IS& H) Gurugram -II, Registration Officer Cum Assessing Authority, Government of Haryana22 Nov 2019

Other filings

Other filings

6 files
Company Name Change Certificate7 Feb 2020Land Tittle Documemts7 Feb 2020Mipl Bs Fy 2018-1928 Nov 2019

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

5 OF 2001 · Monika Infrastructure Pvt.Ltd. · GURGAON-MANESAR

Licence valid to 30 Aug 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

115 OF 2004 · Monika Infrastructure Pvt.Ltd. · GURGAON-MANESAR

Licence valid to 26 Jul 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 28 Nov 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the 2 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

5 OF 2001: 4 parcels, 2.9875 acres in all, in Wazirabad (hadbast 75) and Haidarpur viran (hadbast 76), tehsil Wazirabad.

The licence register prints the licensed area as 2.9718 acres.

  • rectangle 1701, kila 1701/1/2/217 biswa 12 biswansiWazirabad (75)
  • rectangle 19, kila 19/1/23 bigha 3 biswaHaidarpur viran (76)
  • rectangle 18, kila 18/1/11 biswa 2 biswansiHaidarpur viran (76)
  • rectangle 19, kila 19/2/113 biswa 18 biswansiHaidarpur viran (76)

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

115 OF 2004

DTCP’s page showed no land schedule for licence 115 OF 2004 when Bhumiq read it on 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village you want: Wazirabad (hadbast 75) or Haidarpur viran (hadbast 76), tehsil Wazirabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 1701, kila 1701/1/2/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, commercial property
₹4,18,200 per sq yd

this sector, collector rates effective 1 Apr 2026, Wazirabad tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a property is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Site Plan28 Nov 2019Approved Site Plan22 Nov 2019

Layout plan

1 file
Latest Layout Plan22 Nov 2019

Building plans

5 files
BR-III7 Feb 2020BR-III Approval of Revised Building Plan22 Nov 2019Approved Building Plans, Full Set22 Nov 2019Approved Building Plans, Full Set22 Nov 2019Approval Drawing Sld22 Nov 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (56 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/808 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Monika Infrastructure

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.