Tower A & Tower B [part of Project Palm Hills]

by Emaar MGF Land · Sector 77, Gurugram

Not on our price list yet

Possession 31 Aug 2022 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 77, Gurugram1.1 km from Delhi–Gurugram–SNB RRTS, in a straight line
Carpet area
1,218–1,242 sq ft
In m²about 113–115 m², as declared
Registered
1 Jan 2018
Registered by
EMAAR MGF LAND LTD.the company that filed it, for Emaar MGF Land
Timeline
  1. 21 Apr 2011Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 1 Jan 2018Registered with HARERAHARERA, read 4 Nov 2026
  3. 28 Feb 2022Registration valid toHARERA, read 4 Nov 2026
  4. 31 Aug 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

102homes, 1,218 to 1,242 sq ft of carpet area
  • 1,000–1,500 sq ft1,218–1,242 sq ft102

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside1.86 acres in all, by use
  • Roads1.23 acres · 66%
  • Apartment buildings0.33 acres · 18%
  • Parks and playgrounds0.3 acres · 16%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningSplit a.C.
  • KitchenOil bound distemper + tiles
  • Kitchen appliancesIntegrated modular kitchen (upper + lower cabinet) + chimney + hob
  • LiftsS.S. finish inside lift CAR
  • FloorsTile flooring
  • WallsOil bound distemper + tiles
  • BathroomsHigh quality sanitary fittings
  • WindowsUPVC/glass

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 77, GurugramSector 77, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Delhi–Gurugram–SNB RRTS1.1 km
  • Dwarka ExpresswayOpen, 17 Aug 20252.6 km
  • Sohna Elevated Corridor (NH-248A)6.4 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 21 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 19
  • Registered, no OC or CC yet: 1
  • Other register states: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is Tower A & Tower B [part of Project Palm Hills] registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 01 OF 2018, registered on 1 Jan 2018. Ended 28 Feb 2022. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for Tower A & Tower B [part of Project Palm Hills]?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Aug 2022. Its registration runs to 28 Feb 2022; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Tower A & Tower B [part of Project Palm Hills]?From the records · Map pin and road lines, read 6 Sep 2026

Tower A & Tower B [part of Project Palm Hills] is in Sector 77, Gurugram; the site address declared to HARERA is Sector-77, Gurugram. In a straight line it is about 1.1 km from Delhi–Gurugram–SNB RRTS, 2.6 km from Dwarka Expressway and 6.4 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Tower A & Tower B [part of Project Palm Hills]?From the records · HARERA, read 4 Nov 2026

Tower A & Tower B [part of Project Palm Hills] is a Emaar MGF Land project, registered by its company EMAAR MGF LAND LTD..

The source ↗Emaar MGF Land's projects and court record

The records

What the registers hold for Tower A & Tower B [part of Project Palm Hills]: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 01 OF 2018: Registration expired. Ended 28 Feb 2022.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 56 OF 2009 is on the DTCP register: Licence lapsed; the register prints its validity to 30 Aug 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 21 Apr 2011, building plans 21 Apr 2011.Declared to HARERA, read 29 Oct 2026
The court record of Emaar MGF Land’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 28 Feb 2022. HARERA Gurugram, read 4 Nov 2026. Source

  • Red flag: Licence 56 OF 2009 lapsed

    Named in this project’s application. Valid to 30 Aug 2024; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Red flag: Licence 62 OF 2013 lapsed

    Named in this project’s application. Valid to 4 Aug 2019; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 31 HARERA files, with the dates we read them
Registration no.
01 OF 2018
Registration date
1 Jan 2018
Registration valid till
28 Feb 2022
Declared possession
31 Aug 2022

Declared by the promoter to HARERA

Land area
1.86 (Acre) (7,527.15 sq m)
FAR
the application prints 174.98, which is not a ratio
licence
56 of 2009 62 of 2013
Estimated project cost
₹64.01 crore
Layout plan, declared approved (field 5a)
21 Apr 2011
Building plans, declared approved
21 Apr 2011
Completion declared for
31 Aug 2022
Declared inventory · 4 types

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type B15 -01- 3 BHK · 25 units · 113.158 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type B15 -01- 3 BHK · 26 units · 115.416 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type B15 -02- 3 BHK · 25 units · 113.158 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type B15 -02- 3 BHK · 26 units · 115.416 sq m carpet · one flat
Statutory approvals, as declared · 8

Statutory approvals, as declared

  • I. LICENSE 56 OF 2009 — declared: already been obtained (31 Aug 2009)
  • II. LOI — declared: already been obtained (13 Aug 2009)
  • III. AIRPORT HEIGHT CLEARANCE — declared: already been obtained (5 May 2014)
  • IV. FIRE SCHEME APPROVAL — declared: already been obtained (19 Apr 2017)
  • V. SERVICE PLAN ESTIMATES — declared: already been obtained (17 Nov 2016)
  • VI. BUILDING PLANS — declared: already been obtained (21 Apr 2011)
  • VII. ENVIRONMENT CLEARANCE — declared: already been obtained (29 Oct 2010)
  • VIII. LC-IV — declared: already been obtained (31 Aug 2009)
On file with HARERA · 31 files

On file with HARERA (31)

Plans

Site plan

2 files
Superimposed Site Plan10 Jul 2020Approved Site Plan6 Feb 2020

Layout plan

2 files
Layout Plan13 Mar 2020Latest Layout Plan6 Feb 2020

Zoning plan

1 file
Zoning Plan13 Mar 2020

Building plans

2 files
Approved Building Plans, Full Set13 Mar 2020BR III13 Mar 2020

Services

Service plans

3 files
Approved Service Plan Estimate13 Mar 2020Service Plan Estimates Drawings13 Mar 2020Service Plans on the Layout30 Jan 2020

Approvals and clearances

Occupation certificate (OC)

1 file
Occupation Certificate28 Jul 2023

DTCP licence

4 files
LC-IV13 Mar 2020LOI13 Mar 2020License 56 and 62( Palm Hills)13 Mar 2020Licence Copy with Land Schedule30 Jan 2020

Environment clearance

1 file
Environmental Clearance13 Mar 2020

Fire safety

1 file
Approved of Fire Fighting Scheme13 Mar 2020

Other NOCs and clearances

2 files
NOC from Forest Dept to Emaarmgf13 Mar 2020AAI13 Mar 2020

Land records

Land records

2 files
Revenue Record Entry of Licence and Collaboration10 Jul 2020Palm Hills- NEC13 Mar 2020

Sales papers

Allotment and sale agreements

1 file
BBA13 Mar 2020

Money

Accounts and finance

7 files
CA Certificate on the Application’s Figures10 Jul 2020Board Resolution for Operating Bank Accounts10 Jul 2020Cash Flow Statement10 Jul 2020

The promoter’s papers

Declarations and affidavits

2 files
Rep-II13 Mar 2020The Promoter’s Declaration on Affidavit6 Feb 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

56 OF 2009 · Robin Software Pvt Ltd · GURGAON-MANESAR

Licence valid to 30 Aug 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

62 OF 2013 · Robin Software Pvt Ltd · GURGAON-MANESAR

Licence valid to 4 Aug 2019

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 6 Feb 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the 2 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

56 OF 2009

DTCP’s page showed no land schedule for licence 56 OF 2009 when Bhumiq read it on 18 Oct 2026. verify at source

62 OF 2013: 8 parcels, 4.8703 acres in all, in Shikohpur (hadbast 160), tehsil Manesar.

The licence register prints the same licensed area, 4.87 acres.

  • rectangle 914, kila 110 biswa 12 biswansi
  • rectangle 915, kila 91514 biswa
  • rectangle 916, kila 115 biswa
  • rectangle 916, kila 22 bigha
Show the other 4 parcels
  • rectangle 766, kila 213 biswa 8 biswansi
  • rectangle 920, kila 219 biswa 8 biswansi
  • rectangle 767, kila 19 biswa 9 biswansi
  • rectangle 763, kila 7631 bigha 14 biswa

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Shikohpur (hadbast 160), tehsil Manesar. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 914, kila 1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No collector rate for a residential flat in this sector in the lists Bhumiq reads, as of 28 Aug 2026. That is not confirmation that none exists.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Superimposed Site Plan10 Jul 2020Approved Site Plan6 Feb 2020

Layout plan

2 files
Layout Plan13 Mar 2020Latest Layout Plan6 Feb 2020

Building plans

2 files
Approved Building Plans, Full Set13 Mar 2020BR III13 Mar 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (31 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1236 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Emaar MGF Land

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.