Amaltaas Tower (Tower-B)
by Raheja Developers · Sector 99, Gurugram
Not on our price list yet
Possession 27 Aug 2022 · as the developer declared it to HARERA
About this project
Key facts
- Location
- Sector 99, Gurugram0.5 km from Dwarka Expressway, in a straight linePrices and what changed
- Registered by
- RAHEJA DEVELOPERS LTD.the company that filed it, for Raheja Developers
- 2 Jan 2017Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
- 6 Jul 2017Registered with HARERAHARERA, read 4 Nov 2026
- 5 Jul 2022Registration valid toHARERA, read 4 Nov 2026
- 27 Aug 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026
Homes on offer
The homes the developer declared to HARERA, by size.
- Under 1,000 sq ft807–975 sq ft116
- 1,000–1,500 sq ft1,083–1,251 sq ft11
- 1,500–2,000 sq ft1,676–1,845 sq ft10
Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 2 rows of a single unit, because the form lists homes, shops and other buildings in one table.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
- Dwarka ExpresswayOpen, 17 Aug 20250.5 km
- Delhi–Gurugram–SNB RRTS5.6 km
- Sohna Elevated Corridor (NH-248A)7.3 km
Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.
Map data © OpenStreetMap contributors.
The builder
- Other register states: 15
Other projects nearby
8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.
| Project | Builder | Distance | Stage | Asking rate | Possession |
|---|---|---|---|---|---|
Assotech BlithNo photo on file yet | Assotech Moonshine Urban Developers | Same sector | — | — | — |
Project Phase-1No photo on file yet | Satya Townships | Same sector | — | — | — |
SOVEREIGN PARK (PHASE-II)No photo on file yet | Vatika Sovereign Park | Same sector | — | — | — |
No photo of the project on file yet | Raheja Developers | Same sector | — | — | 27 Aug 2022 |
| Pareena Infrastructures | Same sector | — | — | 30 Jun 2022 | |
HabitatNo photo on file yet | Prime Infradevelopers | Same sector | — | — | 30 Nov 2019 |
Cosmos Express 99/Cascade GardensNo photo on file yet | Shvinandan Buildtech | Same sector | — | — | — |
THE ELITE RESIDENCES/ EXPRESS HEIGHTSNo photo on file yet | Shivanandani Buildtech | Same sector | — | — | 14 Sep 2020 |
Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.
Questions buyers ask
Is Amaltaas Tower (Tower-B) registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as 18 OF 2017, registered on 6 Jul 2017. The register’s record shows an end date of 5 Jul 2022. The register shows it as: Registration lapsed.
The source ↗What is the possession timeline for Amaltaas Tower (Tower-B)?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 27 Aug 2022. Its registration runs to 5 Jul 2022; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around Amaltaas Tower (Tower-B)?From the records · Map pin and road lines, read 6 Sep 2026
Amaltaas Tower (Tower-B) is in Sector 99, Gurugram; the site address declared to HARERA is Raheja Vanya Sector-99-A, Gurugram. In a straight line it is about 0.5 km from Dwarka Expressway, 5.6 km from Delhi–Gurugram–SNB RRTS and 7.3 km from Sohna Elevated Corridor (NH-248A).
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building Amaltaas Tower (Tower-B)?From the records · HARERA, read 4 Nov 2026
Amaltaas Tower (Tower-B) is a Raheja Developers project, registered by its company RAHEJA DEVELOPERS LTD..
The source ↗Raheja Developers's projects and court recordThe records
What the registers hold for Amaltaas Tower (Tower-B): registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration 18 OF 2017: Registration lapsed. The register’s record shows an end date of 5 Jul 2022.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Land licence 64 OF 2013 is on the DTCP register: Licence lapsed; the register prints its validity to 19 Jul 2017.DTCP, read 3 Nov 2026
- Plans approved, as the developer declared: layout plan 2 Jan 2017, building plans 2 Jan 2017.Declared to HARERA, read 29 Oct 2026
Flagged on the record
These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.
Red flag: Licence 64 OF 2013 lapsed
Named in this project’s application. Valid to 19 Jul 2017; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source
Red flag: Licence 72 OF 2014 lapsed
Named in this project’s application. Valid to 31 Jul 2019; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source
Amber flag: Registration lapsed
The register’s record shows an end date of 5 Jul 2022. HARERA Gurugram, read 4 Nov 2026. Source
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 12 HARERA files, with the dates we read them
- Registration no.
- 18 OF 2017
- Registration date
- 6 Jul 2017
- Registration valid till
- 5 Jul 2022
- Declared possession
- 27 Aug 2022
Declared by the promoter to HARERA
- Land area
- 2.21 (Acre) (8,943.55 sq m)
- FAR
- 3.86 proposed of 0 permissible
- licence
- 64 of 2013 and 72 of 2014
- Estimated project cost
- ₹98.29 crore
- Cost of land
- ₹25.54 crore
- Layout plan, declared approved (field 5a)
- 2 Jan 2017
- Building plans, declared approved
- 2 Jan 2017
- Completion declared for
- 27 Aug 2022
Declared inventory · 12 types
Declared inventory — 12 types declared, first 8 shown
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 1-(2-BHK-A) · 85 units · 74.93 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 2- (2-BHK-A +TERRACE) · 18 units · 74.93 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 3-( 2-BHK-A+SERVENT ROOM) · 9 units · 90.601 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 4-(2-BHK-A+TERRACE+ SERVENT ROOM) · 4 units · 90.601 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 5-( 3-BHK-A · 3 units · 100.58 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 6 –( 3-BHK-A-WITH TERRACE+SERVENT ROOM · 2 units · 116.25 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 7- (3-BHK-A +SERVENT ROOM) · 1 unit · 116.25 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE 8-( 3-BHK-A-WITH TERRACE · 6 units · 100.58 sq m carpet · one flat
Statutory approvals, as declared · 9
Statutory approvals, as declared
- I. AAI APPROVAL — declared: already been obtained (31 Oct 2014)
- II. WATER SUPPLY ASSURANCE — declared: already been obtained (17 Apr 2017)
- III. SEWERAGE CONNECTION FOR STP — declared: already been obtained (21 Apr 2017)
- IV. ASSURANCE CERTIFICATE OF POWER SUPPLY — declared: already been obtained (18 Nov 2014)
- V. ENVIRONMENT CLEARANCE — declared: already been obtained (30 Nov 2017)
- VI. HUDA NOC FOR CONSTRUCTION — declared: already been obtained (6 Jun 2017)
- VII. NOC FOR NON ARAVALLI HILLS — declared: already been obtained (17 Apr 2013)
- VIII. NON FOREST NOC — declared: already been obtained (18 Mar 2013)
- IX. RAINWATER HARVESTING NOC — declared: already been obtained (9 Feb 2017)
On file with HARERA · 12 files
On file with HARERA (12)
Plans
Site plan
1 fileLayout plan
1 fileZoning plan
1 fileDemarcation plan
1 fileBuilding plans
1 fileServices
Service plans
1 fileApprovals and clearances
DTCP licence
1 fileLand records
Land records
1 fileMoney
Accounts and finance
3 filesThe promoter’s papers
Declarations and affidavits
1 fileThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The 2 DTCP licences named on the application
64 OF 2013 · Raheja Developers Pvt. Ltd. · GURGAON-MANESAR
Licence valid to 19 Jul 2017
From the Town & Country Planning department’s licence register, read 3 Nov 2026.
72 OF 2014 · Raheja Developers Ltd. · GURGAON-MANESAR
Licence valid to 31 Jul 2019
From the Town & Country Planning department’s licence register, read 3 Nov 2026.
A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.
declared in the registration application (Form REP-I), Gurugram bench · submitted 15 Jan 2020 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026
Land under the 2 licences
The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.
64 OF 2013: 13 parcels, 10.1062 acres in all, in Gopalpur (hadbast 47, tehsil Harsaru) and Dhankot (hadbast 49, tehsil Kadipur).
The licence register prints the same licensed area, 10.11 acres.
- 45//18 kanalGopalpur (47)
- 45//108 kanalGopalpur (47)
- 45//11/24 kanal 4 marlaGopalpur (47)
- 45//128 kanalGopalpur (47)
Show the other 9 parcels
- 45//28 kanalGopalpur (47)
- 45//20/14 kanal 18 marlaGopalpur (47)
- 45//38 kanalGopalpur (47)
- 45//98 kanalGopalpur (47)
- 43//23/29 kanalGopalpur (47)
- 111//14 min7 marlaDhankot (49)
- 111//135 kanal 13 marlaDhankot (49)
- 111//179 marlaDhankot (49)
- 111//188 kanal 6 marlaDhankot (49)
The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.
From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source
72 OF 2014: 4 parcels, 2.3806 acres in all, in Dhankot (hadbast 49, tehsil Kadipur) and Gopalpur (hadbast 47, tehsil Harsaru).
The licence register prints the same licensed area, 2.38 acres.
- 111//147 kanal 13 marlaDhankot (49)
- rectangle 111, kila 73 kanal 13 marlaDhankot (49)
- rectangle 111, kila 174 kanal 19 marla 8 sarsaiDhankot (49)
- 45//11/1/22 kanal 15 marlaGopalpur (47)
The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.
From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source
Who owns this land today, or is it mortgaged?
The Bhumiq team checks it with you.
Check it yourself on jamabandi.nic.in
- Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
- Pick district Gurugram, then the tehsil and the village you want: Gopalpur (hadbast 47, tehsil Harsaru) or Dhankot (hadbast 49, tehsil Kadipur). The site lists villages in Hindi, so the hadbast number is the surer match.
- Pick the latest year, then a from the list here, such as 45//1.
- Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.
Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.
- Collector rate, residential flat
- ₹6,000 per sq ft
Sector 99, collector rates effective 1 Apr 2026, Kadipur tehsil. Source
Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.
Worked out on this page. Not saved or sent.
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
1 fileLayout plan
1 fileBuilding plans
1 fileAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (12 in all), none is a floor plan or a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/1179 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Raheja Developers
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.