SOUTH DRIVE
by Divya Buildcon · Sector 69, Gurugram
Not on our price list yet
Possession 31 Dec 2026 · as the developer declared it to HARERA
About this project
Key facts
- Location
- Sector 69, Gurugram0.8 km from Sohna Elevated Corridor (NH-248A), in a straight line
- Registered by
- DIVYA BUILDCON PRIVATE LIMITEDthe company that filed it, for Divya Buildcon
- 15 Dec 2022Layout plan approveddeclared to HARERA, read 29 Oct 2026
- 12 Jan 2024Building plans approveddeclared to HARERA, read 29 Oct 2026
- 31 Dec 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026
Amenities and specifications
How the land is set aside and what comes in each home, as the developer declared them to HARERA.
- Roads1.268 acres · 60%
- Plots for sale0.737 acres · 35%
- Other usesas the form names them: Underground water tank utility area, STP (sewage treatment plant)0.064 acres · 3%
- Electricity sub-station0.037 acres · 2%
The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
- Sohna Elevated Corridor (NH-248A)0.8 km
- Delhi–Gurugram–SNB RRTS4.6 km
- Dwarka ExpresswayOpen, 17 Aug 20254.7 km
Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.
Map data © OpenStreetMap contributors.
The builder
- Registered, no OC or CC yet: 1
Other projects nearby
8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.
| Project | Builder | Distance | Stage | Asking rate | Possession |
|---|---|---|---|---|---|
No photo of the project on file yet | Tulip Infratech | Same sector | — | — | 6 Feb 2019 |
No photo of the project on file yet | Ocean Seven Buildtech | Same sector | — | — | 13 Feb 2023 |
TRUMP RESIDENCES GURGAONNo photo on file yet | Riverday Infrastructure | Same sector | — | — | 30 Apr 2033 |
No photo of the project on file yet | Tulip Infratech | Same sector | — | — | 6 Feb 2019 |
![]() | Smartworld Developers | Same sector | Under construction | ₹20,000/sq ft | 31 May 2032 |
No photo of the project on file yet | Tulip Infratech | Same sector | — | — | 31 Aug 2019 |
No photo of the project on file yet | Tulip Infratech | Same sector | — | — | 31 Dec 2027 |
| DLF Home Developers | 1.1 kmto its sector’s point | — | — | 10 Nov 2027 |
Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.
Questions buyers ask
Is SOUTH DRIVE registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as GGM/778/510/2024/05. Valid to 31 Dec 2026.
The source ↗What is the possession timeline for SOUTH DRIVE?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 31 Dec 2026. Its registration runs to 31 Dec 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around SOUTH DRIVE?From the records · Map pin and road lines, read 6 Sep 2026
SOUTH DRIVE is in Sector 69, Gurugram; the site address declared to HARERA is Sector -69, Gurugram Manesar Urban Complex, Haryana. In a straight line it is about 0.8 km from Sohna Elevated Corridor (NH-248A), 4.6 km from Delhi–Gurugram–SNB RRTS and 4.7 km from Dwarka Expressway.
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building SOUTH DRIVE?From the records · HARERA, read 4 Nov 2026
SOUTH DRIVE is a Divya Buildcon project, registered by its company DIVYA BUILDCON PRIVATE LIMITED.
The source ↗Divya Buildcon's projects and court recordThe records
What the registers hold for SOUTH DRIVE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration GGM/778/510/2024/05: Registered. Valid to 31 Dec 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Land licence 206 OF 2022 is on the DTCP register, valid to 13 Dec 2027.DTCP, read 3 Nov 2026
- Plans approved, as the developer declared: layout plan 15 Dec 2022, building plans 12 Jan 2024.Declared to HARERA, read 29 Oct 2026
Flagged on the record
These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.
Amber flag: Registration ends soon
Valid to 31 Dec 2026. HARERA Gurugram, read 4 Nov 2026. Source
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 39 HARERA files, with the dates we read them
- Registration no.
- GGM/778/510/2024/05
- Registration valid till
- 31 Dec 2026
- Declared possession
- 31 Dec 2026
Declared by the promoter to HARERA
- Land area
- 2.10625 (Acre) (8,523.69 sq m)
- FAR
- 1.5 proposed of 1.5 permissible
- licence
- 206 of 2022 dated 14.12.2022
- Estimated project cost
- ₹41.82 crore
- Cost of land
- ₹12.54 crore
- Layout plan, declared approved (field 5a)
- 15 Dec 2022
- Building plans, declared approved
- 12 Jan 2024
- Construction to start
- 1 Nov 2023
- Completion declared for
- 31 Dec 2026
Statutory approvals, as declared · 4
Statutory approvals, as declared
- I. LICENCE — declared: already been obtained (14 Dec 2022)
- II. SERVICE ESTIMATE — declared: already been obtained (2 Jan 2024)
- III. STANDARD DESIGN — declared: already been obtained (12 Jan 2024)
- IV. LAYOUT PLAN — declared: already been obtained (15 Dec 2022)
On file with HARERA · 39 files
On file with HARERA (39)
Plans
Site plan
1 fileLayout plan
2 filesDemarcation plan
1 fileServices
Sewerage and drainage
2 filesWater supply
1 fileRoads
1 fileService plans
1 fileApprovals and clearances
DTCP licence
2 filesLand records
Land records
6 filesMoney
Accounts and finance
4 filesThe promoter’s papers
Declarations and affidavits
1 fileCompany papers
1 fileOther filings
Other filings
16 filesThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
206 OF 2022 · DIVYA BUILDCON PVT. LTD · GURGAON-MANESAR
Licence valid to 13 Dec 2027
From the Town & Country Planning department’s licence register, read 3 Nov 2026.
A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.
declared in the registration application (Form REP-I), Gurugram bench · submitted 28 Sept 2023 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026
Land under the licence
The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.
206 OF 2022: 4 parcels, 2.1063 acres in all, in Noorpur jharsa (hadbast 165), tehsil Badshahpur.
The licence register prints the same licensed area, 2.1063 acres.
- 1//135 kanal 12 marla
- 1//14/16 kanal
- 1//18/2/12 kanal 5 marla
- 1//7/33 kanal
The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.
From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source
Who owns this land today, or is it mortgaged?
The Bhumiq team checks it with you.
Check it yourself on jamabandi.nic.in
- Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
- Pick district Gurugram, then the tehsil and the village: Noorpur jharsa (hadbast 165), tehsil Badshahpur. The site lists villages in Hindi, so the hadbast number is the surer match.
- Pick the latest year, then a from the list here, such as 1//13.
- Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.
Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.
Collector rate
No one collector rate can be matched to this project's type.
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
1 fileLayout plan
2 filesAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (39 in all), none is a building plan, a floor plan or a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/2586 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Divya Buildcon
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.