Skip to content

SOUTH DRIVE

by Divya Buildcon · Sector 69, Gurugram

Not on our price list yet

Possession 31 Dec 2026 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 69, Gurugram0.8 km from Sohna Elevated Corridor (NH-248A), in a straight line
Registered by
DIVYA BUILDCON PRIVATE LIMITEDthe company that filed it, for Divya Buildcon
Timeline
  1. 15 Dec 2022Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 12 Jan 2024Building plans approveddeclared to HARERA, read 29 Oct 2026
  3. 31 Dec 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside2.106 acres in all, by use
  • Roads1.268 acres · 60%
  • Plots for sale0.737 acres · 35%
  • Other usesas the form names them: Underground water tank utility area, STP (sewage treatment plant)0.064 acres · 3%
  • Electricity sub-station0.037 acres · 2%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 69, GurugramSector 69, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Sohna Elevated Corridor (NH-248A)0.8 km
  • Delhi–Gurugram–SNB RRTS4.6 km
  • Dwarka ExpresswayOpen, 17 Aug 20254.7 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is SOUTH DRIVE registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/778/510/2024/05. Valid to 31 Dec 2026.

The source ↗
What is the possession timeline for SOUTH DRIVE?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2026. Its registration runs to 31 Dec 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around SOUTH DRIVE?From the records · Map pin and road lines, read 6 Sep 2026

SOUTH DRIVE is in Sector 69, Gurugram; the site address declared to HARERA is Sector -69, Gurugram Manesar Urban Complex, Haryana. In a straight line it is about 0.8 km from Sohna Elevated Corridor (NH-248A), 4.6 km from Delhi–Gurugram–SNB RRTS and 4.7 km from Dwarka Expressway.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building SOUTH DRIVE?From the records · HARERA, read 4 Nov 2026

SOUTH DRIVE is a Divya Buildcon project, registered by its company DIVYA BUILDCON PRIVATE LIMITED.

The source ↗Divya Buildcon's projects and court record

The records

What the registers hold for SOUTH DRIVE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/778/510/2024/05: Registered. Valid to 31 Dec 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 206 OF 2022 is on the DTCP register, valid to 13 Dec 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 15 Dec 2022, building plans 12 Jan 2024.Declared to HARERA, read 29 Oct 2026
The court record of Divya Buildcon’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 31 Dec 2026. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 39 HARERA files, with the dates we read them
Registration no.
GGM/778/510/2024/05
Registration valid till
31 Dec 2026
Declared possession
31 Dec 2026

Declared by the promoter to HARERA

Land area
2.10625 (Acre) (8,523.69 sq m)
FAR
1.5 proposed of 1.5 permissible
licence
206 of 2022 dated 14.12.2022
Estimated project cost
₹41.82 crore
Cost of land
₹12.54 crore
Layout plan, declared approved (field 5a)
15 Dec 2022
Building plans, declared approved
12 Jan 2024
Construction to start
1 Nov 2023
Completion declared for
31 Dec 2026
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. LICENCE — declared: already been obtained (14 Dec 2022)
  • II. SERVICE ESTIMATE — declared: already been obtained (2 Jan 2024)
  • III. STANDARD DESIGN — declared: already been obtained (12 Jan 2024)
  • IV. LAYOUT PLAN — declared: already been obtained (15 Dec 2022)
On file with HARERA · 39 files

On file with HARERA (39)

Plans

Site plan

1 file
Approved Site Plan28 Sept 2023

Layout plan

2 files
App Std Design Layout Plan23 May 2024Latest Layout Plan28 Sept 2023

Demarcation plan

1 file
Demarcation Plan28 Sept 2023

Services

Sewerage and drainage

2 files
Drg Sewer Layout23 May 2024Drg Storm Water Drg23 May 2024

Water supply

1 file
Drg Water Supply Scheme23 May 2024

Roads

1 file
Drg Road Layout23 May 2024

Service plans

1 file
Approval of SPE23 May 2024

Approvals and clearances

DTCP licence

2 files
LOI2 Sept 2023Licence Copy with Land Schedule2 Sept 2023

Land records

Land records

6 files
Jamabandi23 May 2024Aks Sazra23 May 2024Mutation23 May 2024

Money

Accounts and finance

4 files
Cash Flow Statement24 May 2024Non-Default Certificate from a CA28 Sept 2023CA Certificate on the Application’s Figures28 Sept 2023Demand Drafts5 Sept 2023

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit23 May 2024

Company papers

1 file
Board Resolution5 Sept 2023

Other filings

Other filings

16 files
Plot A-02 B-0823 May 2024Plot C-0423 May 2024Plot D02 D0823 May 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

206 OF 2022 · DIVYA BUILDCON PVT. LTD · GURGAON-MANESAR

Licence valid to 13 Dec 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 28 Sept 2023 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

206 OF 2022: 4 parcels, 2.1063 acres in all, in Noorpur jharsa (hadbast 165), tehsil Badshahpur.

The licence register prints the same licensed area, 2.1063 acres.

  • 1//135 kanal 12 marla
  • 1//14/16 kanal
  • 1//18/2/12 kanal 5 marla
  • 1//7/33 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Noorpur jharsa (hadbast 165), tehsil Badshahpur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 1//13.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan28 Sept 2023

Layout plan

2 files
App Std Design Layout Plan23 May 2024Latest Layout Plan28 Sept 2023

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (39 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2586 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Divya Buildcon

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.