Tulip Lemon

by Tulip Infratech · Sector 69, Gurugram

Not on our price list yet

Possession 6 Feb 2019 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 69, Gurugram0.8 km from Sohna Elevated Corridor (NH-248A), in a straight linePrices and what changed
Carpet area
3,080–3,836 sq ft
In m²about 286–356 m², as declared
Registered
2 Aug 2017
Registered by
PREMIUM INFRATECH PVT LTDthe company that filed it, for Tulip Infratech
Timeline
  1. 23 Dec 2014Layout and building plans approveddeclared to HARERA, read 15 Oct 2026
  2. 2 Aug 2017Registered with HARERAHARERA, read 4 Nov 2026
  3. 6 Feb 2019Possession, as declareddeclared to HARERA, read 15 Oct 2026
  4. 23 Nov 2019Registration valid toHARERA, read 4 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

754homes, 3,080 to 3,836 sq ft of carpet area
  • 3,000 sq ft and above3,080–3,836 sq ft754

Carpet area per home, as declared to HARERA (read 15 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

In each home
  • KitchenMarble/granite counter with sink
  • LiftsCapacity 10 & 13 person, KONE or eqivalent
  • FloorsCeramic tiles or equivalent
  • WallsWhite WASH
  • BathroomsWhite sanitary, CP fitting and mirror
  • WindowsHardwood/ shutter window
  • Main doorFlush door
  • Electrical fittingsSwitches only (no lights & fixtures)

The developer’s specifications in the HARERA application, declared to HARERA, read 15 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 69, GurugramSector 69, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Sohna Elevated Corridor (NH-248A)0.8 km
  • Delhi–Gurugram–SNB RRTS4.6 km
  • Dwarka ExpresswayOpen, 17 Aug 20254.7 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 9 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 2
  • Registered, no OC or CC yet: 4
  • Other register states: 3

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is Tulip Lemon registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 31 OF 2017, registered on 2 Aug 2017. Ended 23 Nov 2019. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for Tulip Lemon?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 6 Feb 2019. Its registration runs to 23 Nov 2019; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Tulip Lemon?From the records · Map pin and road lines, read 6 Sep 2026

Tulip Lemon is in Sector 69, Gurugram; the site address declared to HARERA is Sector 69 & 70, Gurugram. In a straight line it is about 0.8 km from Sohna Elevated Corridor (NH-248A), 4.6 km from Delhi–Gurugram–SNB RRTS and 4.7 km from Dwarka Expressway.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Tulip Lemon?From the records · HARERA, read 4 Nov 2026

Tulip Lemon is a Tulip Infratech project, registered by its company PREMIUM INFRATECH PVT LTD.

The source ↗Tulip Infratech's projects and court record

The records

What the registers hold for Tulip Lemon: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 31 OF 2017: Registration expired. Ended 23 Nov 2019.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 132 OF 2014 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 24 Aug 2019.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 23 Dec 2014, building plans 23 Dec 2014.Declared to HARERA, read 15 Oct 2026
The court record of Tulip Infratech’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 23 Nov 2019. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 132 OF 2014 validity ended

    Named in this project’s application. Valid to 24 Aug 2019. The register links a completion certificate (LC-IX), dated 2 Jul 2021, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 14 HARERA files, with the dates we read them
Registration no.
31 OF 2017
Registration date
2 Aug 2017
Registration valid till
23 Nov 2019
Declared possession
6 Feb 2019

Declared by the promoter to HARERA

Land area
5.06875 (Acre) (20,512.5 sq m)
FAR
the application prints 225, which is not a ratio
licence
Licence No 132 of 2014 dated 27.08.2014
Estimated project cost
the application prints ₹136.71 lakh crore, which is not a plausible figure
Cost of land
the application prints ₹51.39 lakh crore, which is not a plausible figure
Layout plan, declared approved (field 5a)
23 Dec 2014
Building plans, declared approved
23 Dec 2014
Construction to start
20 Sept 2017
Completion declared for
6 Feb 2019
Declared inventory · 2 types

Declared inventory

  • Apartment/Shops/Other Buildings · 714 units · 356.373 sq m carpet · 6 towers · one flat
  • Apartment/Shops/Other Buildings · 40 units · 286.138 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. SITE PLAN — declared: already been obtained (23 Dec 2014)
On file with HARERA · 14 files

On file with HARERA (14)

Plans

Site plan

1 file
Approved Site Plan19 Feb 2020

Layout plan

1 file
Latest Layout Plan20 Feb 2020

Zoning plan

1 file
Zoning Plan19 Feb 2020

Demarcation plan

1 file
Demarcation Plan19 Feb 2020

Building plans

1 file
Approved Building Plans, Full Set20 Feb 2020

Services

Service plans

1 file
Service Plans on the Layout19 Feb 2020

Approvals and clearances

Occupation certificate (OC)

1 file
OC uploaded4 Aug 2023

Completion certificate (CC)

1 file
CC uploaded4 Aug 2023

DTCP licence

1 file
Licence Copy with Land Schedule19 Feb 2020

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration20 Feb 2020

Money

Accounts and finance

3 files
Non-Default Certificate from a CA20 Feb 2020CA Certificate on the Application’s Figures20 Feb 2020Cash Flow Statement20 Feb 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit19 Feb 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

132 OF 2014 · Premium Infratech Pvt. Ltd. C/o Tulip Infratech · GURGAON-MANESAR

Licence valid to 24 Aug 2019

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 20 Feb 2020 · read 15 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

132 OF 2014: 10 parcels, 5.0687 acres in all, in Badshapur (hadbast 87), tehsil Badshahpur.

The licence register prints the same licensed area, 5.07 acres.

  • 78//5/14 kanal 8 marla
  • 78//5/2/118 marla
  • 78//6 min3 kanal 1 marla
  • 77//2/1/26 kanal 1 marla
Show the other 6 parcels
  • 77//2/2/215 marla
  • 77//37 kanal 2 marla
  • 77//87 kanal 16 marla
  • 77//98 kanal
  • rectangle 77, kila 1/12 kanal 3 marla 3 sarsai
  • rectangle 77, kila 2/1/1/16 marla 6 sarsai

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Badshapur (hadbast 87), tehsil Badshahpur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 78//5/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, residential flat
₹6,950 per sq ft

Sector 69, collector rates effective 1 Apr 2026, Badshahpur tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan19 Feb 2020

Layout plan

1 file
Latest Layout Plan20 Feb 2020

Building plans

1 file
Approved Building Plans, Full Set20 Feb 2020

Among the uploads Bhumiq read from HARERA's page on 15 Oct 2026 (14 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1289 · read 15 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Tulip Infratech

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.